17082 W BOLLINGER DR 90272

Certificate Information: 17082 W BOLLINGER DR 90272

Application / Permit
25010-30000-03567
Plan Check / Job No.
B25WL06412
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
Issued on 11/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/7/2025 APPLICANT
Assigned to Plan Check Engineer 8/11/2025 JOE VO
Corrections Issued 8/12/2025 JOE VO
Quality Review Completed 8/21/2025 KEN GILL
Building Plans Picked Up 8/27/2025 APPLICANT
Plan Check Approved 9/25/2025 JOE VO
Issued 11/17/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/12/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 8/12/2025 DERRICK MAGEE
Sewer availability Cleared 8/12/2025 DERRICK MAGEE
Hydrant and Access approval Cleared 8/25/2025 JOHN CONNEALLY
Low Impact Development (LID) Cleared 8/26/2025 LUIS LUVANO
Grading Pre-Inspection Cleared 9/18/2025 LANNY MERRICK

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Nittay Inc; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2025 Partial Inspection BOBBY KEY
Underground Mechanical 12/5/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 12/8/2025 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 12/12/2025 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 12/16/2025 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 12/17/2025 Conditional Approval BOBBY KEY
Deputy Steel/Welding 12/17/2025 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 12/23/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 12/23/2025 Not Ready for Inspection DANIEL VERA
Underground Mechanical 12/30/2025 Partial Approval BOBBY KEY
Wood Frame 12/31/2025 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/5/2026 Partial Approval BOBBY KEY
Underground Mechanical 1/5/2026 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Partial Approval BOBBY KEY
Deputy Wood Construction 1/8/2026 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 1/12/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/13/2026 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/17/2026 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 2/17/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Approved BOBBY KEY
HVAC-Rough 2/17/2026 Corrections Issued BOBBY KEY
PLUMBING-Rough 2/17/2026 Approved BOBBY KEY
Shower Pan 2/23/2026 Not Ready for Inspection DANIEL VERA
Shower Pan 2/24/2026 Approved BOBBY KEY
Interior/Exterior Lathing 2/26/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 3/18/2026 Approved Pending GreenApproval BOBBY KEY
Green Building Rough 3/18/2026 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 3/18/2026 Approved BOBBY KEY
Insulation 3/23/2026 Corrections Issued DANIEL VERA
Interior/Exterior Lathing 3/23/2026 Partial Approval DANIEL VERA
Drywall Nailing 3/31/2026 Not Ready for Inspection BOBBY KEY
Insulation 3/31/2026 Approved BOBBY KEY
Drywall Nailing 4/2/2026 Approved BOBBY KEY