1011 N FISKE ST 90272

Certificate Information: 1011 N FISKE ST 90272

Application / Permit
25010-30000-03474
Plan Check / Job No.
B25WL06306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 65'-1" x 31'-1". NFPA 13D SPRINKLERS THROUGHOUT. EO1 MAINTAIN PORTION OF EXISTING FDN --1 of 2 ---
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
CofO Issued on 6/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/1/2025 EDWIN ESPIN
Corrections Issued 8/5/2025 EDWIN ESPIN
Quality Review Completed 8/6/2025 CHIHARU SUZUKI
Building Plans Picked Up 8/6/2025 APPLICANT
Plan Check Approved 9/9/2025 EDWIN ESPIN
Issued 9/9/2025 APPLICANT
CofO in Progress 6/24/2026 TEMISTOCLES CAAL
Permit Finaled 6/24/2026 RICHARD STEINBACH
CofO Issued 6/24/2026 RICHARD STEINBACH
Permit Finaled 6/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/4/2025 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 8/4/2025 JOHN LIN
Roof/Waste drainage to street Cleared 8/4/2025 JOHN LIN
Sewer availability Cleared 8/4/2025 JOHN LIN
Hydrant and Access approval Cleared 8/15/2025 RUEL COLE

Contact Information

Contractor Albino Construction Inc; Lic. No.: 477121-B 12568 W WASHINGTON BLVD   SUITE 200    LOS ANGELES, CA 90066
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 10/8/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 10/8/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Corrections Issued MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 1/16/2026 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 1/20/2026 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 1/20/2026 Approved BOBBY KEY
Green Building Rough 1/20/2026 Not Ready for Inspection BOBBY KEY
HVAC-Rough 1/20/2026 Approved BOBBY KEY
PLUMBING-Rough 1/20/2026 Approved BOBBY KEY
Interior/Exterior Lathing 1/28/2026 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/2/2026 Approved TEMISTOCLES CAAL
Green Building Rough 2/2/2026 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 2/2/2026 Approved TEMISTOCLES CAAL
Shower Pan 2/5/2026 Approved TEMISTOCLES CAAL
Insulation 2/13/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 2/13/2026 Approved MICHAEL ALLEN
Drywall Nailing 2/19/2026 Approved TEMISTOCLES CAAL
Gas Test 3/11/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/15/2026 Conditional Approval DANIEL VERA
HVAC-Final 4/15/2026 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 5/7/2026 Approved MICHAEL ALLEN
HVAC-Final 5/7/2026 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 5/7/2026 Not Ready for Inspection MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Not Ready MICHAEL ALLEN
HVAC-Final 5/11/2026 Approved TEMISTOCLES CAAL
PLUMBING-Final 5/11/2026 Approved TEMISTOCLES CAAL
Final 5/22/2026 Corrections Issued TEMISTOCLES CAAL
Green Building Final 5/22/2026 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 5/22/2026 Approved TEMISTOCLES CAAL
Smoke Detectors 5/22/2026 Approved TEMISTOCLES CAAL
Final 5/29/2026 Corrections Issued JUAN VALENZUELA
Final 6/24/2026 OK to Issue CofO TEMISTOCLES CAAL