1011 N FISKE ST 90272
Certificate Information: 1011 N FISKE ST 90272
- Application / Permit
- 25010-30000-03474
- Plan Check / Job No.
- B25WL06306
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 65'-1" x 31'-1". NFPA 13D SPRINKLERS THROUGHOUT. EO1 MAINTAIN PORTION OF EXISTING FDN --1 of 2 ---
- Permit Issued
- Issued on 9/9/2025
- Issuing Office
- Current Status
- CofO Issued on 6/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2025 | EDWIN ESPIN |
| Corrections Issued | 8/5/2025 | EDWIN ESPIN |
| Quality Review Completed | 8/6/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/6/2025 | APPLICANT |
| Plan Check Approved | 9/9/2025 | EDWIN ESPIN |
| Issued | 9/9/2025 | APPLICANT |
| CofO in Progress | 6/24/2026 | TEMISTOCLES CAAL |
| Permit Finaled | 6/24/2026 | RICHARD STEINBACH |
| CofO Issued | 6/24/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/24/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2025 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 8/4/2025 | JOHN LIN |
| Sewer availability | Cleared | 8/4/2025 | JOHN LIN |
| Hydrant and Access approval | Cleared | 8/15/2025 | RUEL COLE |
Contact Information
| Contractor | Albino Construction Inc; Lic. No.: 477121-B | 12568 W WASHINGTON BLVD SUITE 200 LOS ANGELES, CA 90066 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/16/2026 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 1/20/2026 | Approved | BOBBY KEY |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 1/20/2026 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/20/2026 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/2/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 2/2/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 2/5/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/13/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/13/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 2/19/2026 | Approved | TEMISTOCLES CAAL |
| Gas Test | 3/11/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/15/2026 | Conditional Approval | DANIEL VERA |
| HVAC-Final | 4/15/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 5/7/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 5/7/2026 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 5/7/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | MICHAEL ALLEN |
| HVAC-Final | 5/11/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/11/2026 | Approved | TEMISTOCLES CAAL |
| Final | 5/22/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 5/22/2026 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 5/22/2026 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 5/22/2026 | Approved | TEMISTOCLES CAAL |
| Final | 5/29/2026 | Corrections Issued | JUAN VALENZUELA |
| Final | 6/24/2026 | OK to Issue CofO | TEMISTOCLES CAAL |