756 N JACON WAY 90272

Certificate Information: 756 N JACON WAY 90272

Application / Permit
25010-30000-03333
Plan Check / Job No.
B25WL06109
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/25/2025 APPLICANT
Assigned to Plan Check Engineer 7/29/2025 EDWIN ESPIN
Corrections Issued 7/31/2025 EDWIN ESPIN
Quality Review Completed 8/1/2025 CHIHARU SUZUKI
Applicant returned to address corrections 8/28/2025 EDWIN ESPIN
Applicant returned to address corrections 9/25/2025 EDWIN ESPIN
Plan Check Approved 9/30/2025 EDWIN ESPIN
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/31/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/31/2025 CINDY QI
Roof/Waste drainage to street Cleared 7/31/2025 CINDY QI
Sewer availability Cleared 7/31/2025 CINDY QI
Hydrant and Access approval Cleared 9/3/2025 LAVEON RIDER

Contact Information

Contractor Pacific Image Builders Inc; Lic. No.: 804559-B 1369 E WALDON WAY      FRESNO, CA 93730
Engineer Baxter,, David; Lic. No.: S6332 380 BUCKSKIN LN      NORCO, CA 92860
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Strong,, Darren E; Lic. No.: C73106 15327 CALABRIA CT      BAKERSFIELD, CA 93314
Engineer Theaker,, Ronald Clive; Lic. No.: L9722 3896 DEAN DR      VENTURA, CA 93003

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2025 Partial Approval BOBBY KEY
Sewer 10/20/2025 Approved BOBBY KEY
Footing/Foundation/Slab 10/28/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 10/30/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 12/19/2025 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 1/12/2026 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Drilled-In Anchors 1/14/2026 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 2/9/2026 Approved BOBBY KEY
ELECTRICAL-Rough 2/9/2026 Approved BOBBY KEY
Green Building Rough 2/9/2026 Approved BOBBY KEY
HVAC-Rough 2/9/2026 Approved BOBBY KEY
PLUMBING-Rough 2/9/2026 Approved BOBBY KEY
Verify Sprinkler Sign Off 2/9/2026 Approved BOBBY KEY
Shower Pan 2/19/2026 Approved BOBBY KEY
Insulation 3/11/2026 Approved EVAN COOPER
Drywall Nailing 3/19/2026 Approved BOBBY KEY