756 N JACON WAY 90272
Certificate Information: 756 N JACON WAY 90272
- Application / Permit
- 25010-30000-03333
- Plan Check / Job No.
- B25WL06109
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- Issued on 9/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2025 | EDWIN ESPIN |
| Corrections Issued | 7/31/2025 | EDWIN ESPIN |
| Quality Review Completed | 8/1/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 8/28/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/25/2025 | EDWIN ESPIN |
| Plan Check Approved | 9/30/2025 | EDWIN ESPIN |
| Issued | 9/30/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/31/2025 | CINDY QI |
| Sewer availability | Cleared | 7/31/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 9/3/2025 | LAVEON RIDER |
Contact Information
| Contractor | Pacific Image Builders Inc; Lic. No.: 804559-B | 1369 E WALDON WAY FRESNO, CA 93730 |
| Engineer | Baxter,, David; Lic. No.: S6332 | 380 BUCKSKIN LN NORCO, CA 92860 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Engineer | Strong,, Darren E; Lic. No.: C73106 | 15327 CALABRIA CT BAKERSFIELD, CA 93314 |
| Engineer | Theaker,, Ronald Clive; Lic. No.: L9722 | 3896 DEAN DR VENTURA, CA 93003 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/20/2025 | Partial Approval | BOBBY KEY |
| Sewer | 10/20/2025 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 10/28/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 10/30/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/19/2025 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/12/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 1/14/2026 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/9/2026 | Approved | BOBBY KEY |
| Green Building Rough | 2/9/2026 | Approved | BOBBY KEY |
| HVAC-Rough | 2/9/2026 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/9/2026 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 2/9/2026 | Approved | BOBBY KEY |
| Shower Pan | 2/19/2026 | Approved | BOBBY KEY |
| Insulation | 3/11/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 3/19/2026 | Approved | BOBBY KEY |