950 N EMBURY ST 90272
Certificate Information: 950 N EMBURY ST 90272
- Application / Permit
- 25010-30000-03269
- Plan Check / Job No.
- B25WL06009
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
- Permit Issued
- Issued on 10/1/2025
- Issuing Office
- Current Status
- Issued on 10/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | SERGIO SILVA |
| Corrections Issued | 7/31/2025 | SERGIO SILVA |
| Quality Review Completed | 8/1/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/4/2025 | APPLICANT |
| Applicant returned to address corrections | 9/25/2025 | SERGIO SILVA |
| Plan Check Approved | 10/1/2025 | SERGIO SILVA |
| Issued | 10/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2025 | SAFA JAVANMARDI |
| Permit | Cleared | 7/30/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/30/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/30/2025 | SAFA JAVANMARDI |
| Trees in Parkway | Cleared | 8/1/2025 | RICHARD SANCHEZ |
| Hydrant and Access approval | Cleared | 8/6/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 8/7/2025 | ERNEST TSE |
| GPI Written Notices | Cleared | 10/1/2025 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 10/1/2025 | SERGIO SILVA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Surur,, Shereef C; Lic. No.: L7295 | 2029 MILLCREEK WY PALMDALE, CA 93551 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | Waddell,, Ian R; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Ruberti,, Rudolph F; Lic. No.: EG1708 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/3/2025 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 12/9/2025 | Approved | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/11/2025 | Approved | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 12/12/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 1/16/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/28/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 1/30/2026 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 2/5/2026 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/9/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/19/2026 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 2/19/2026 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 2/19/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/20/2026 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 2/20/2026 | Conditional Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/26/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/6/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 3/6/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/6/2026 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 3/6/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 3/11/2026 | Conditional Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/18/2026 | Partial Approval | MICHAEL ALLEN |
| Drywall Nailing | 3/23/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/6/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 4/6/2026 | Approved | TEMISTOCLES CAAL |