7836 S DUNBARTON AVE 90045
Certificate Information: 7836 S DUNBARTON AVE 90045
- Application / Permit
- 25010-30000-03244
- Plan Check / Job No.
- B25WL05954
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story single family residence w/new attached garage and attached ADU per GC 66323(a)(1) w/post tension concrete slab and roof truss
- Permit Issued
- Issued on 10/1/2025
- Issuing Office
- Current Status
- Issued on 10/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | JOHN TRIANTAFYLLOS |
| Assigned to Zoning Architect | 7/24/2025 | NICOLE SALEEBA |
| Corrections Issued | 7/31/2025 | JOHN TRIANTAFYLLOS |
| Quality Review Completed | 8/11/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/12/2025 | APPLICANT |
| Plan Check Approved | 9/25/2025 | JOHN TRIANTAFYLLOS |
| Issued | 10/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2025 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2025 | CHRISTINE REUSCH |
| Hydrant and Access approval | Cleared | 8/8/2025 | GILBERT URREA |
| CPC | Cleared | 8/13/2025 | DAVID URITA |
| CPC | Cleared | 8/13/2025 | DAVID URITA |
| CPC | Cleared | 8/13/2025 | DAVID URITA |
| Permit | Cleared | 8/13/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/13/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/13/2025 | LEE GUILBEAUX |
| Specific Plan | Cleared | 8/26/2025 | RICHARD WOO |
| Zoning Plan Check | Cleared | 9/3/2025 | NICOLE SALEEBA |
| GPI Written Notices | Cleared | 9/25/2025 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 9/25/2025 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | Waddell,, Ian R; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Landscape Architect | Schulz,, William F; Lic. No.: LA1547 | 5281 CALIFORNIA AVE STE 350 IRVINE, CA 92617 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/5/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 12/9/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 12/11/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 1/16/2026 | No Access for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 1/21/2026 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 1/21/2026 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 1/21/2026 | Corrections Issued | JESUS PINEDA |
| METHANE-Barrier | 1/21/2026 | Not Ready for Inspection | JESUS PINEDA |
| METHANE-Subgrade | 1/21/2026 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 2/5/2026 | Approved | JESUS PINEDA |
| Deputy Pre-Stress Concrete | 2/6/2026 | Conditional Approval | ANDREW NAVE |
| Deputy Pre-Stress Concrete | 2/24/2026 | Conditional Approval | DAVID FEILER |
| Deputy Wood Construction | 2/24/2026 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 3/26/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/8/2026 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 4/10/2026 | No Access for Inspection | RUBEN RIVAS |
| HVAC-Rough | 4/10/2026 | No Access for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 4/10/2026 | No Access for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/14/2026 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 4/14/2026 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/14/2026 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 4/14/2026 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 4/14/2026 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 4/14/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/4/2026 | Approved | JESUS PINEDA |
| Insulation | 5/13/2026 | Conditional Approval | MICHAEL LEWIS |
| Insulation | 5/20/2026 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 6/1/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/1/2026 | Partial Approval | MORRIS JACKSON |