1043 N HARTZELL ST 90272
Certificate Information: 1043 N HARTZELL ST 90272
- Application / Permit
- 25010-30000-03118
- Plan Check / Job No.
- B25WL05697
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND HABITABLE BASEMENT, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/18/2025
- Issuing Office
- Current Status
- Issued on 9/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2025 | RARES BODEA |
| Corrections Issued | 7/17/2025 | RARES BODEA |
| Quality Review Completed | 7/21/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/23/2025 | APPLICANT |
| Applicant returned to address corrections | 8/28/2025 | RARES BODEA |
| Plan Check Approved | 9/11/2025 | RARES BODEA |
| Issued | 9/18/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2025 | CINDY QI |
| Permit | Cleared | 7/17/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/17/2025 | CINDY QI |
| Sewer availability | Cleared | 7/17/2025 | CINDY QI |
| Low Impact Development (LID) | Cleared | 7/28/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 7/31/2025 | PATRICK PEREZ |
| Permit | Cleared | 8/6/2025 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 8/28/2025 | CALOSHA APPROVED |
Contact Information
| Architect | Carson, Han, William; Lic. No.: C31806 | 719 N FAIRFAX AVE SUITE C LOS ANGELES, CA 90046 |
| Contractor | M D M Builders Group; Lic. No.: 933238-B | 541 SOUTH SPRING ST STE 213 LOS ANGELES, CA 90013 |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/2/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Shotcrete | 1/6/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Shotcrete | 1/7/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/7/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Shotcrete | 1/12/2026 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 1/28/2026 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 2/13/2026 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/13/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 3/3/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Partial Approval | MICHAEL ALLEN |
| Wood Frame | 3/4/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 4/1/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2026 | Partial Approval | EVAN COOPER |
| Structural Steel Frame | 4/2/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/14/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/29/2026 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 6/10/2026 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 6/10/2026 | Partial Approval | TEMISTOCLES CAAL |