858 N FISKE ST 90272

Certificate Information: 858 N FISKE ST 90272

Application / Permit
25010-30000-03068
Plan Check / Job No.
B25WL05611
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/25/2025
Issuing Office
Current Status
CofO Issued on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 EDWIN ESPIN
Corrections Issued 7/15/2025 EDWIN ESPIN
Quality Review Completed 7/16/2025 CHIHARU SUZUKI
Building Plans Picked Up 7/17/2025 APPLICANT
Plan Check Approved 7/25/2025 EDWIN ESPIN
Issued 7/25/2025 APPLICANT
CofO in Progress 6/8/2026 JESUS PINEDA
Permit Finaled 6/8/2026 RICHARD STEINBACH
Permit Finaled 6/8/2026 RICHARD STEINBACH
CofO Issued 6/8/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/14/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/14/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/14/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/14/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 7/23/2025 JOHN CONNEALLY

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Dolan Design & Build Llc; Lic. No.: 1135363-B 1817 IOWA TRAIL      TOPANGA,, CA 90290
Engineer Chrysostomo,, Anderson; Lic. No.: L9216 20 CIVIC CENTER DRIVE      SANTA ANA, CA 92701
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/20/2025 Partial Approval TEMISTOCLES CAAL
Sewer 8/20/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 8/27/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/27/2025 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 8/27/2025 Approved STEPHANIE SWANSON
Deputy Wood Construction 9/8/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 10/1/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 10/9/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 10/15/2025 Approved STEPHANIE SWANSON
PLUMBING-Rough 10/15/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 11/6/2025 Approved TEMISTOCLES CAAL
Green Building Rough 11/6/2025 Approved TEMISTOCLES CAAL
Shower Pan 11/6/2025 Not Ready for Inspection TEMISTOCLES CAAL
Verify Sprinkler Sign Off 11/6/2025 Approved TEMISTOCLES CAAL
Insulation 11/18/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 11/18/2025 Partial Approval TEMISTOCLES CAAL
Drywall Nailing 12/3/2025 Approved MEL KHACHATOURIAN
Shower Pan 12/3/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 12/16/2025 Approved TEMISTOCLES CAAL
Underground Mechanical 3/2/2026 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 3/17/2026 Approved DANIEL VERA
Underground Mechanical 4/10/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/21/2026 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 4/30/2026 Approved MICHAEL ALLEN
Gas Test 5/5/2026 Approved TEMISTOCLES CAAL
PLUMBING-Final 5/5/2026 Approved TEMISTOCLES CAAL
HVAC-Final 5/14/2026 Approved JESUS PINEDA
Final 5/27/2026 Corrections Issued JESUS PINEDA
Green Building Final 5/27/2026 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Approved JESUS PINEDA
Service/Power Release 5/27/2026 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 5/27/2026 Approved JESUS PINEDA
Green Building Final 5/28/2026 Approved JESUS PINEDA
Service/Power Release 5/28/2026 Approved JESUS PINEDA
Final 6/8/2026 OK to Issue CofO JESUS PINEDA