858 N FISKE ST 90272
Certificate Information: 858 N FISKE ST 90272
- Application / Permit
- 25010-30000-03068
- Plan Check / Job No.
- B25WL05611
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | EDWIN ESPIN |
| Corrections Issued | 7/15/2025 | EDWIN ESPIN |
| Quality Review Completed | 7/16/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/17/2025 | APPLICANT |
| Plan Check Approved | 7/25/2025 | EDWIN ESPIN |
| Issued | 7/25/2025 | APPLICANT |
| CofO in Progress | 6/8/2026 | JESUS PINEDA |
| Permit Finaled | 6/8/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/8/2026 | RICHARD STEINBACH |
| CofO Issued | 6/8/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 7/23/2025 | JOHN CONNEALLY |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Dolan Design & Build Llc; Lic. No.: 1135363-B | 1817 IOWA TRAIL TOPANGA,, CA 90290 |
| Engineer | Chrysostomo,, Anderson; Lic. No.: L9216 | 20 CIVIC CENTER DRIVE SANTA ANA, CA 92701 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/20/2025 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 8/20/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/27/2025 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/27/2025 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/8/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 10/1/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 10/9/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 10/15/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/15/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 11/6/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/18/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | TEMISTOCLES CAAL |
| Drywall Nailing | 12/3/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 12/3/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/16/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 3/2/2026 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 3/17/2026 | Approved | DANIEL VERA |
| Underground Mechanical | 4/10/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/21/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 4/30/2026 | Approved | MICHAEL ALLEN |
| Gas Test | 5/5/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/5/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 5/14/2026 | Approved | JESUS PINEDA |
| Final | 5/27/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 5/27/2026 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 5/27/2026 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 5/27/2026 | Approved | JESUS PINEDA |
| Green Building Final | 5/28/2026 | Approved | JESUS PINEDA |
| Service/Power Release | 5/28/2026 | Approved | JESUS PINEDA |
| Final | 6/8/2026 | OK to Issue CofO | JESUS PINEDA |