15346 W DE PAUW ST 90272
Certificate Information: 15346 W DE PAUW ST 90272
- Application / Permit
- 25010-30000-03060
- Plan Check / Job No.
- B25WL05579
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, NFPA 13D SPRINKLERS THROUGHOUT --- 1 of 2 ---
- Permit Issued
- Issued on 9/23/2025
- Issuing Office
- Current Status
- Issued on 9/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | EDWIN ESPIN |
| Corrections Issued | 7/15/2025 | EDWIN ESPIN |
| Quality Review Completed | 7/16/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/21/2025 | APPLICANT |
| Applicant returned to address corrections | 9/16/2025 | EDWIN ESPIN |
| Plan Check Approved | 9/23/2025 | EDWIN ESPIN |
| Issued | 9/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2025 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2025 | ABDULLAH SADOZAI |
| Permit | Cleared | 7/16/2025 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 7/16/2025 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 7/16/2025 | ABDULLAH SADOZAI |
| Low Impact Development (LID) | Cleared | 8/4/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 8/22/2025 | PATRICK PEREZ |
Contact Information
| Contractor | T M C General Contractors Inc; Lic. No.: 603053-B | 15415 SUNSET BLVD SUITE 230 PACIFIC PALISADES, CA 90272 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
| Engineer | Schmahl,, Lawrence Joseph; Lic. No.: L5748 | 11209 HOWARD STREET WHITTIER, CA 90606 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 11/6/2025 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/7/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 11/10/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/4/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 12/11/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/12/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 12/18/2025 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/18/2025 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/19/2025 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/23/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/23/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/6/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/6/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/8/2026 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2026 | Approved | STEPHANIE SWANSON |
| Deputy Steel/Welding | 1/23/2026 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/28/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Steel/Welding | 2/26/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 3/9/2026 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 5/8/2026 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/15/2026 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/3/2026 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/10/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/12/2026 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/18/2026 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 6/18/2026 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 6/18/2026 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/18/2026 | Partial Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 6/18/2026 | Approved | STEPHANIE SWANSON |
| Shower Pan | 6/30/2026 | Approved | STEPHANIE SWANSON |
| Insulation | 7/6/2026 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 7/20/2026 | Approved | ARAM AVEDISIAN |
| Insulation | 7/20/2026 | Approved | ARAM AVEDISIAN |