1179 N AMALFI DR 90272
Certificate Information: 1179 N AMALFI DR 90272
- Application / Permit
- 25010-30000-02942
- Plan Check / Job No.
- B25WL05398
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/19/2025
- Issuing Office
- Current Status
- Issued on 9/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2025 | EDWIN ESPIN |
| Corrections Issued | 7/9/2025 | EDWIN ESPIN |
| Quality Review Completed | 7/14/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/15/2025 | APPLICANT |
| Applicant returned to address corrections | 8/5/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/2/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/16/2025 | EDWIN ESPIN |
| Plan Check Approved | 9/16/2025 | EDWIN ESPIN |
| Issued | 9/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/10/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/10/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/10/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/10/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/10/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/10/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2025 | CINDY QI |
| Permit | Cleared | 7/10/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/10/2025 | CINDY QI |
| Sewer availability | Cleared | 7/10/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 7/22/2025 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 7/31/2025 | RICHARD SANCHEZ |
| GPI Written Notices | Cleared | 8/7/2025 | EDWIN ESPIN |
| Grading Pre-Inspection | Cleared | 8/7/2025 | EDWIN ESPIN |
| Excavation more than 5-ft deep | Cleared | 9/2/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
| Engineer | Hanna,, John; Lic. No.: C71506 | P.O. BOX 3203 PASO ROBLES, CA 93447 |
| Engineer | Zhou,, Gangyi; Lic. No.: M34279 | 26439 RANCHO PARKWAY STE 120 LAKE FOREST, CA 92630 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2026 |
Inspection Request History
| Pre-Inspection | 10/7/2025 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/25/2025 | Partial Approval | KENNETH NAGLE |
| Reinforced Masonry Frame | 12/8/2025 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 1/7/2026 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/27/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/12/2026 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 2/12/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 2/24/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 3/4/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/5/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/5/2026 | Approved | TEMISTOCLES CAAL |
| Sewer | 3/5/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | TEMISTOCLES CAAL |