- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2025 | SELLA BENYAMIN |
| Corrections Issued | 7/3/2025 | SELLA BENYAMIN |
| Quality Review Completed | 7/3/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/8/2025 | APPLICANT |
| Plan Check Approved | 8/12/2025 | SELLA BENYAMIN |
| Issued | 8/12/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
| CofO Issued | 2/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2025 | JOHN LIN |
| Sewer availability | Cleared | 7/7/2025 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 7/9/2025 | VISHAL MANDALIA |
| Low Impact Development (LID) | Cleared | 7/22/2025 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 7/29/2025 | LAVEON RIDER |
Contact Information
| Contractor | Pacific Southwest Builders Inc; Lic. No.: 553992-B | 703 PIER AVE SUITE B #706 HERMOSA BEACH, CA 90254 |
| Engineer | Guzman,, Martin; Lic. No.: S7287 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/25/2025 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/15/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/19/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/26/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 9/26/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/26/2025 | Approved | BOBBY KEY |
| Shower Pan | 9/26/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/29/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/29/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/1/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 10/2/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | BOBBY KEY |
| Green Building Rough | 10/6/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 10/6/2025 | Approved | BOBBY KEY |
| Insulation | 10/10/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 10/15/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/1/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 12/8/2025 | Approved | BOBBY KEY |
| Service/Power Release | 12/9/2025 | Approved | BOBBY KEY |
| Gas Test | 12/17/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/17/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/22/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 12/23/2025 | Corrections Issued | DANIEL VERA |
| Final | 12/30/2025 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/30/2025 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 12/30/2025 | Approved | BOBBY KEY |
| HVAC-Final | 12/30/2025 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 12/30/2025 | Approved | BOBBY KEY |
| Final | 1/2/2026 | OK to Issue CofO | BOBBY KEY |
| Footing/Foundation/Slab | 1/2/2026 | Approved | BOBBY KEY |
| HVAC-Final | 1/2/2026 | Approved | BOBBY KEY |