1023 N FISKE ST 90272
Certificate Information: 1023 N FISKE ST 90272
- Application / Permit
- 25010-30000-02840
- Plan Check / Job No.
- B25WL05215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- Issued on 10/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | EDWIN ESPIN |
| Corrections Issued | 6/30/2025 | EDWIN ESPIN |
| Quality Review Completed | 7/2/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/3/2025 | APPLICANT |
| Applicant returned to address corrections | 9/30/2025 | EDWIN ESPIN |
| Plan Check Approved | 10/3/2025 | EDWIN ESPIN |
| Issued | 10/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | MICHAEL BROWN |
| Permit | Cleared | 7/15/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/15/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 7/24/2025 | LAVEON RIDER |
| Trees in Parkway | Cleared | 7/28/2025 | RICHARD SANCHEZ |
| GPI Written Notices | Cleared | 9/14/2025 | EDWIN ESPIN |
| Grading Pre-Inspection | Cleared | 9/14/2025 | EDWIN ESPIN |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Sowa Development Inc; Lic. No.: 961853-B | 2629 33RD STREET SANTA MONICA, CA 90405 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 5140 YOLANDA AVE TARZANA, CA 91356 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Landscape Architect | Harris,, Gabrielle Love; Lic. No.: LA5520 | 4580 STATE ROUTE 364 CANANDAIGUA, NY 14424 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/16/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/30/2025 | Approved | BOBBY KEY |
| Deputy Wood Construction | 1/28/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Conditional Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/10/2026 | Conditional Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/2/2026 | Approved | EVAN COOPER |
| HVAC-Rough | 4/2/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/2/2026 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 5/4/2026 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/14/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 5/14/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/14/2026 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 5/14/2026 | Approved | JESUS PINEDA |
| Insulation | 5/20/2026 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/27/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 6/22/2026 | Approved | EVAN COOPER |