304 E 84TH ST 90003
Certificate Information: 304 E 84TH ST 90003
- Application / Permit
- 25010-30000-02834
- Plan Check / Job No.
- B25WL05207
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU. PER GC 66323(a)(4)
- Permit Issued
- Issued on 9/5/2025
- Issuing Office
- Metro
- Current Status
- Issued on 9/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2025 | ALFREDO JARA |
| Corrections Issued | 6/29/2025 | ALFREDO JARA |
| Building Plans Picked Up | 7/2/2025 | APPLICANT |
| Plan Check Approved | 9/2/2025 | ALFREDO JARA |
| Issued | 9/5/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 7/15/2025 | JEREMY CHOK |
| Address approval | Cleared | 7/17/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 7/18/2025 | JEREMY CHOK |
| Tenant Habitability Plan | Cleared | 8/19/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| Sewer | 2/2/2026 | Corrections Issued | JOHN QUINTANILLA |
| Sewer | 2/9/2026 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/25/2026 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 2/27/2026 | Approved | JOHN QUINTANILLA |
| Wood Frame | 3/13/2026 | Corrections Issued | JOHN QUINTANILLA |
| Wood Frame | 3/20/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2026 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 3/21/2026 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/21/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 4/21/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/21/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/24/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 4/24/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/24/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/30/2026 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 4/30/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/30/2026 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2026 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/4/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/11/2026 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/11/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/13/2026 | Corrections Issued | JOHN QUINTANILLA |
| Shower Pan | 5/13/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2026 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/19/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/26/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 5/26/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/26/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 5/26/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Corrections Issued | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 6/2/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 6/3/2026 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 6/3/2026 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/3/2026 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 6/3/2026 | Partial Inspection | RAUL BARAJAS |