16777 W BOLLINGER DR 90272
Certificate Information: 16777 W BOLLINGER DR 90272
- Application / Permit
- 25010-30000-02748
- Plan Check / Job No.
- B25WL05072
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, BASEMENT (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Current Status
- Issued on 8/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2025 | EDWIN ESPIN |
| Corrections Issued | 6/23/2025 | EDWIN ESPIN |
| Assigned to Zoning Architect | 6/23/2025 | EDWIN ESPIN |
| Quality Review Completed | 6/25/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/26/2025 | APPLICANT |
| Applicant returned to address corrections | 7/17/2025 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/7/2025 | EDWIN ESPIN |
| Plan Check Approved | 8/12/2025 | EDWIN ESPIN |
| Issued | 8/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/15/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 8/2/2025 | GILBERT URREA |
Contact Information
| Architect | James,, Donald Philip; Lic. No.: C23353 | 15 MAPLE DRIVE ALISO VIEJO, CA 92656 |
| Contractor | Landmark Building & Design Inc; Lic. No.: 982610-B | 4717 VAN NUYS BLVD STE 104 SHERMAN OAKS, CA 91403 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
| Engineer | Quayum,, Mohammad M.; Lic. No.: C74111 | 1863 CHURCH ST SIMI VALLEY, CA 93065 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/9/2026 |
| Verify Sprinkler Sign Off | 6/9/2026 |
| Green Building Rough | 6/9/2026 |
Inspection Request History
| Footing/Foundation/Slab | 9/30/2025 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 10/2/2025 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/22/2025 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 10/23/2025 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 10/23/2025 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/4/2025 | Conditional Approval | BOBBY KEY |
| Masonry Wall/Backfill | 11/13/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/8/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 12/8/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/8/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/8/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Corrections Issued | DANIEL VERA |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 12/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 12/22/2025 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/3/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 5/1/2026 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 5/6/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Partial Approval | DANIEL VERA |
| ELECTRICAL-Rough | 5/15/2026 | Conditional Approval | DANIEL VERA |
| HVAC-Rough | 5/28/2026 | Approved | MICHAEL ALLEN |