1437 N JONESBORO DR 90049
Certificate Information: 1437 N JONESBORO DR 90049
- Application / Permit
- 25010-30000-02585
- Plan Check / Job No.
- B25WL04786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED A.D.U. PER GCS 66323 (a)(2) with sprinkler through-out.
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | BEHROUZ KHOKHAR |
| Corrections Issued | 7/7/2025 | BEHROUZ KHOKHAR |
| Quality Review Completed | 7/14/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/15/2025 | APPLICANT |
| Plan Check Approved | 11/3/2025 | BEHROUZ KHOKHAR |
| Issued | 11/13/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2025 | DARIN LAM |
| Sewer availability | Cleared | 7/13/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 9/23/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 10/22/2025 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/24/2025 | CARLOS AGUILERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Dolan Design & Build Llc; Lic. No.: 1135363-B | 1817 IOWA TRAIL TOPANG, CA 90290 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 7/27/2026 |
Inspection Request History
| PLUMBING-Rough | 1/16/2026 | Corrections Issued | HERBERT GIRON |
| Sewer | 1/16/2026 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 1/20/2026 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 1/27/2026 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 2/2/2026 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 2/4/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/6/2026 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 2/11/2026 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2026 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Approved | HERBERT GIRON |
| HVAC-Rough | 5/5/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/11/2026 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 5/11/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 5/19/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/22/2026 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 6/22/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/22/2026 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/22/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/25/2026 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 6/29/2026 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/29/2026 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 7/1/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 7/2/2026 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 7/2/2026 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 7/2/2026 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/7/2026 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 7/7/2026 | Approved | HERBERT GIRON |
| Insulation | 7/9/2026 | Approved | HERBERT GIRON |