1437 N JONESBORO DR 90049

Certificate Information: 1437 N JONESBORO DR 90049

Application / Permit
25010-30000-02585
Plan Check / Job No.
B25WL04786
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED A.D.U. PER GCS 66323 (a)(2) with sprinkler through-out.
Permit Issued
Issued on 11/13/2025
Issuing Office
West Los Angeles
Current Status
Issued on 11/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 BEHROUZ KHOKHAR
Corrections Issued 7/7/2025 BEHROUZ KHOKHAR
Quality Review Completed 7/14/2025 CHIHARU SUZUKI
Building Plans Picked Up 7/15/2025 APPLICANT
Plan Check Approved 11/3/2025 BEHROUZ KHOKHAR
Issued 11/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/12/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/13/2025 DARIN LAM
Sewer availability Cleared 7/13/2025 DARIN LAM
Hydrant and Access approval Cleared 9/23/2025 JOHN CONNEALLY
Low Impact Development (LID) Cleared 10/22/2025 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/24/2025 CARLOS AGUILERA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Dolan Design & Build Llc; Lic. No.: 1135363-B 1817 IOWA TRAIL      TOPANG, CA 90290
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Nguyen,, Huan; Lic. No.: C64238 15 STUDEBAKER      IRVINE, CA 92618

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 7/27/2026   

Inspection Request History

PLUMBING-Rough 1/16/2026 Corrections Issued HERBERT GIRON
Sewer 1/16/2026 Conditional Approval HERBERT GIRON
PLUMBING-Rough 1/20/2026 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 1/27/2026 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/2/2026 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 2/4/2026 Approved KEVIN SARGSYAN
PLUMBING-Rough 2/6/2026 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 2/11/2026 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Approved HERBERT GIRON
HVAC-Rough 5/5/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 5/11/2026 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 5/11/2026 Approved HERBERT GIRON
ELECTRICAL-Rough 5/19/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/22/2026 Conditional Approval EVAN COOPER
Green Building Rough 6/22/2026 Approved EVAN COOPER
PLUMBING-Rough 6/22/2026 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 6/22/2026 Approved EVAN COOPER
PLUMBING-Rough 6/25/2026 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 6/29/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 6/29/2026 Not Ready for Inspection HERBERT GIRON
Insulation 7/1/2026 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 7/2/2026 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 7/2/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 7/2/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 7/7/2026 Approved HERBERT GIRON
PLUMBING-Rough 7/7/2026 Approved HERBERT GIRON
Insulation 7/9/2026 Approved HERBERT GIRON