506 N MUSKINGUM PL 90272
Certificate Information: 506 N MUSKINGUM PL 90272
- Application / Permit
- 25010-30000-02487
- Plan Check / Job No.
- B25WL04590
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/5/2025
- Issuing Office
- Current Status
- Issued on 8/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | VU NGUYEN |
| Corrections Issued | 6/6/2025 | VU NGUYEN |
| Quality Review Completed | 6/6/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 7/11/2025 | VU NGUYEN |
| Plan Check Approved | 7/18/2025 | VU NGUYEN |
| Issued | 8/5/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/11/2025 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 7/14/2025 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 7/15/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Borgese Rocco Pasquale; Lic. No.: 852378-B | 739 10TH STREET, UNIT B SANTA MONICA, CA 90402 |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
| Engineer | Stewart,, Charles S; Lic. No.: GE2138 | 2170 HIDDEN HILLS LINCOLN, CA 95648 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/11/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Piling/Pier/Caisson | 8/12/2025 | Partial Approval | BOBBY KEY |
| Reinforced Concrete Frame | 9/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/19/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/10/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/3/2025 | Conditional Approval | HERBERT GIRON |
| Sewer | 11/3/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Steel/Welding | 11/7/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/7/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/10/2025 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 11/13/2025 | Partial Approval | KENNETH NAGLE |
| Deputy Steel/Welding | 12/1/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/1/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 12/3/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 12/10/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 12/30/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 2/26/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 3/6/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 3/11/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Partial Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 4/10/2026 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2026 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/4/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/19/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 5/19/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/20/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 5/20/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/20/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/27/2026 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/27/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/27/2026 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/27/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/2/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Shower Pan | 6/2/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/5/2026 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 6/5/2026 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/12/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/12/2026 | Partial Approval | MEL KHACHATOURIAN |