834 N GALLOWAY ST 90272
Certificate Information: 834 N GALLOWAY ST 90272
- Application / Permit
- 25010-30000-02460
- Plan Check / Job No.
- B25WL04521
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO.
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2025 | VIVIAN LAO |
| Corrections Issued | 6/5/2025 | VIVIAN LAO |
| Quality Review Completed | 6/5/2025 | JOHN FRANCIA |
| Building Plans Picked Up | 6/6/2025 | APPLICANT |
| Applicant returned to address corrections | 6/17/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 6/25/2025 | VIVIAN LAO |
| Plan Check Approved | 7/2/2025 | VIVIAN LAO |
| Issued | 7/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/18/2025 | CINDY QI |
| Sewer availability | Cleared | 6/18/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/24/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
| Engineer | Vardeh,, Edmond; Lic. No.: C56992 | 43 INVERARY TRABUCO CANYON, CA 92679 |
| Geologist | Hogrefe,, Scott Joseph; Lic. No.: EG1516 | 3157 ESCOLLERA AVE SANTA ROSA VALLEY, CA 93012 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/14/2025 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 8/14/2025 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/25/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/23/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 12/11/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 12/22/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 12/29/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 1/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 1/20/2026 | Partial Approval | HERBERT GIRON |
| Shower Pan | 1/20/2026 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/21/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Green Building Rough | 1/21/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 1/21/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/2/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 2/3/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 2/9/2026 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 2/17/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/20/2026 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 4/7/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/15/2026 | Approved | TEMISTOCLES CAAL |