548 N EL MEDIO AVE 90272
Certificate Information: 548 N EL MEDIO AVE 90272
- Application / Permit
- 25010-30000-02412
- Plan Check / Job No.
- B25WL04450
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ** 2025 WILDFIRE PROJECT ** ** ELIGIBLE PROJECT ** REBUILD 1-STORY TYPE VB DETACHED 2-CAR GARAGE WITH ATTACHED STORAGE ROOM. wildfire rebuild
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Current Status
- CofO Issued on 4/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | SERGIO SILVA |
| Corrections Issued | 6/5/2025 | SERGIO SILVA |
| Quality Review Completed | 6/5/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 7/14/2025 | SERGIO SILVA |
| Building Plans Picked Up | 7/15/2025 | APPLICANT |
| Plan Check Approved | 7/28/2025 | SERGIO SILVA |
| Issued | 8/14/2025 | APPLICANT |
| Permit Finaled | 4/14/2026 | JUAN VALENZUELA |
| CofO Issued | 4/14/2026 | JUAN VALENZUELA |
| Permit Finaled | 4/14/2026 | JUAN VALENZUELA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | VISHAL MANDALIA |
| Permit | Cleared | 6/6/2025 | VISHAL MANDALIA |
| Roof/Waste drainage to street | Cleared | 6/6/2025 | VISHAL MANDALIA |
| Hydrant and Access approval | Cleared | 6/26/2025 | LAVEON RIDER |
| Construction near power lines | Cleared | 7/21/2025 | TINA MIRANDA |
Contact Information
| Contractor | L C G Construction; Lic. No.: 497270-B | 27560 WINDING WAY MALIBU, CA 90265 |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 3332 BENNETT DRIVE LOS ANGELES, CA 90068 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/8/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/26/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/26/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 12/12/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/12/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 12/15/2025 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 1/22/2026 | Approved | MEL KHACHATOURIAN |
| Final | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 1/22/2026 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 1/22/2026 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 3/10/2026 | Approved | EVAN COOPER |
| Final | 3/10/2026 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 3/10/2026 | Approved | EVAN COOPER |
| Final | 3/18/2026 | Conditional Approval | MEL KHACHATOURIAN |