3642 S BARRINGTON AVE 90066
Certificate Information: 3642 S BARRINGTON AVE 90066
- Application / Permit
- 25010-30000-02409
- Plan Check / Job No.
- B25WL04444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER GC 66323 (a) (2).
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Current Status
- Issued on 8/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | ZENA HADDIS |
| Corrections Issued | 7/1/2025 | ZENA HADDIS |
| Quality Review Completed | 7/3/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/7/2025 | APPLICANT |
| Plan Check Approved | 8/14/2025 | ZENA HADDIS |
| Issued | 8/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Specific Plan | Cleared | 7/15/2025 | RICHARD WOO |
| Construction near power lines | Cleared | 7/21/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 8/14/2025 | ZENA HADDIS |
| Grading Pre-Inspection | Cleared | 8/14/2025 | ZENA HADDIS |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Leilabi Mehran; Lic. No.: 978316-B | 1200 RANCHERO WY APT 86 SAN JOSE, CA 95117 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2025 | Partial Inspection | KENNETH NAGLE |
| Sewer | 8/28/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 9/22/2025 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/29/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/30/2025 | Conditional Approval | KIRK SANDERS |
| Underground Mechanical | 9/30/2025 | Partial Approval | KIRK SANDERS |
| Pre-Inspection | 1/7/2026 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 1/13/2026 | Approved | HERBERT GIRON |
| HVAC-Rough | 1/16/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 1/30/2026 | Approved | ARAM AVEDISIAN |
| Shower Pan | 2/24/2026 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/11/2026 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 3/19/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/20/2026 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 3/20/2026 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 3/20/2026 | Approved | ARAM AVEDISIAN |
| Insulation | 3/27/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 4/7/2026 | Approved | ANTHONY EGSON |
| Underground Mechanical | 5/12/2026 | Partial Approval | ANDREW NAVE |
| Sewer | 5/18/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 5/20/2026 | Approved | ANDREW NAVE |
| Underground Mechanical | 5/20/2026 | Approved | ANDREW NAVE |