5348 1/2 W THORNBURN ST 90045

Certificate Information: 5348 1/2 W THORNBURN ST 90045

Application / Permit
25010-30000-02380
Plan Check / Job No.
B25WL04366
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 - NEW DETACHED 2-STORY ADU per ordinace LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 8/27/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 BEHROUZ KHOKHAR
Corrections Issued 6/6/2025 YASHAR EMAMI
Quality Review Completed 6/9/2025 CHIHARU SUZUKI
Building Plans Picked Up 6/10/2025 APPLICANT
Applicant returned to address corrections 8/13/2025 YASHAR EMAMI
Applicant returned to address corrections 8/20/2025 YASHAR EMAMI
Plan Check Approved 8/27/2025 YASHAR EMAMI
Plan Check Approved 8/27/2025 YASHAR EMAMI
Plan Check Approved 8/27/2025 YASHAR EMAMI
Issued 8/27/2025 APPLICANT
CofO in Progress 2/17/2026 JESUS PINEDA
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/12/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 6/12/2025 XOCHITL ARQUIETA
Sewer availability Cleared 6/12/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 6/30/2025 HISASHI KOBAYAKAWA
Specific Plan Cleared 7/24/2025 PEDRO AYALA
GPI Written Notices Cleared 8/13/2025 YASHAR EMAMI
Grading Pre-Inspection Cleared 8/13/2025 YASHAR EMAMI

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Adler,, Neal; Lic. No.: C84772 2220 EXPOSITION DR 60      SAN LUIS OBISPO, CA 93401

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/8/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/8/2025 Corrections Issued JESUS PINEDA
Pre-Inspection 9/8/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 9/26/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/26/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 9/30/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 9/30/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 10/6/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval RUBEN RIVAS
Sewer 10/28/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 10/28/2025 Partial Approval RUBEN RIVAS
Sewer 10/31/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 12/11/2025 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 12/11/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/11/2025 Partial Approval ANTHONY EGSON
Shower Pan 12/11/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 12/11/2025 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/11/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/15/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Approved JESUS PINEDA
HVAC-Rough 12/15/2025 Approved JESUS PINEDA
PLUMBING-Rough 12/15/2025 Approved JESUS PINEDA
Shower Pan 12/15/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/23/2025 Approved JESUS PINEDA
Green Building Rough 12/23/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/23/2025 Partial Approval JESUS PINEDA
MERV13>=Rough 12/23/2025 Approved JESUS PINEDA
Verify Sprinkler Sign Off 12/23/2025 Approved JESUS PINEDA
Insulation 12/29/2025 Corrections Issued ANTHONY EGSON
Insulation 12/31/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/31/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/5/2026 Approved JESUS PINEDA
Drywall Nailing 1/5/2026 Approved JESUS PINEDA
Special/Order Compliance 1/5/2026 Partial Inspection DAKOTA LOW
ELECTRICAL-Final 2/4/2026 Conditional Approval JESUS PINEDA
ELECTRICAL-Final 2/11/2026 Approved JESUS PINEDA
Final 2/11/2026 OK to Issue CofO JESUS PINEDA
Green Building Final 2/11/2026 Approved JESUS PINEDA
HVAC-Final 2/11/2026 Approved JESUS PINEDA
MERV13>=Final 2/11/2026 Approved JESUS PINEDA
PLUMBING-Final 2/11/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Not Required JESUS PINEDA
Service/Power Release 2/11/2026 Approved JESUS PINEDA
Smoke Detectors 2/11/2026 Approved JESUS PINEDA