1147 N EMBURY ST 90272

Certificate Information: 1147 N EMBURY ST 90272

Application / Permit
25010-30000-02352
Plan Check / Job No.
B25WL04331
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 7/7/2025
Issuing Office
Current Status
Issued on 7/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/27/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 EDWIN ESPIN
Corrections Issued 6/4/2025 EDWIN ESPIN
Quality Review Completed 6/5/2025 CHIHARU SUZUKI
Building Plans Picked Up 6/9/2025 APPLICANT
Plan Check Approved 7/7/2025 EDWIN ESPIN
Issued 7/7/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/4/2025 LAVEON RIDER
Address approval Cleared 6/17/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/17/2025 CINDY QI
Permit Cleared 6/17/2025 CINDY QI
Roof/Waste drainage to street Cleared 6/17/2025 CINDY QI
Sewer availability Cleared 6/17/2025 CINDY QI
Trees in Parkway Cleared 6/25/2025 RICHARD SANCHEZ
GPI Written Notices Cleared 7/7/2025 EDWIN ESPIN
Grading Pre-Inspection Cleared 7/7/2025 EDWIN ESPIN

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Watson David Construction Inc; Lic. No.: 934184-B 4457 HAZELBROOK AVENUE      LONG BEACH, CA 90808
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2025 Partial Approval TEMISTOCLES CAAL
Sewer 9/12/2025 Approved TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 9/30/2025 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 9/30/2025 Partial Inspection TEMISTOCLES CAAL
Deputy Wood Construction 10/30/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Conditional Approval TEMISTOCLES CAAL
Pre-Inspection 12/11/2025 Partial Inspection DANIEL VERA
HVAC-Rough 12/22/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 2/18/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/18/2026 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 2/18/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/23/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/13/2026 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 4/22/2026 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 5/7/2026 Approved MICHAEL ALLEN
Green Building Rough 5/7/2026 Approved MICHAEL ALLEN
Insulation 5/7/2026 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 5/7/2026 Approved MICHAEL ALLEN
Drywall Nailing 5/26/2026 Approved TEMISTOCLES CAAL
Shower Pan 7/10/2026 Approved JESUS PINEDA