1116 N GALLOWAY ST 90272
Certificate Information: 1116 N GALLOWAY ST 90272
- Application / Permit
- 25010-30000-02297
- Plan Check / Job No.
- B25WL04289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT INELIGIBLE
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | SERGIO SILVA |
| Corrections Issued | 6/11/2025 | SERGIO SILVA |
| Quality Review Completed | 6/12/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/13/2025 | APPLICANT |
| Plan Check Approved | 8/22/2025 | SERGIO SILVA |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | CINDY QI |
| Permit | Cleared | 6/11/2025 | CINDY QI |
| Sewer availability | Cleared | 6/11/2025 | CINDY QI |
| Low Impact Development (LID) | Cleared | 6/17/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/24/2025 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 6/26/2025 | LAVEON RIDER |
| Senate Bill 9 | Cleared | 7/10/2025 | BRENNEN OBETO |
| Miscellaneous | Cleared | 7/30/2025 | SERGIO SILVA |
| Address approval | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 8/15/2025 | BRANDON WONG |
| Low Impact Development (LID) | Cleared | 8/18/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 8/20/2025 | JERRY KAO |
| GPI Written Notices | Cleared | 8/22/2025 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 8/22/2025 | LANNY MERRICK |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | R S C Construction Inc; Lic. No.: 1059714-B | 3617 W 107TH STREET INGLEWOOD, CA 90303 |
| Engineer | Busch,, Matthew Wayne; Lic. No.: L7229 | 29 PONTE BRAVA LAKE ELSINORE, CA 92352 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
| Engineer | Toufighi,, Pejman; Lic. No.: M31480 | 22346 BARCOTTA DRIVE SANTA CLARITA, CA 91350 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 9/5/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 9/9/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/26/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 12/17/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/14/2026 | Corrections Issued | DANIEL VERA |
| HVAC-Rough | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 1/14/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 1/16/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 1/16/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/16/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/9/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/19/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 4/24/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/13/2026 | Approved | TEMISTOCLES CAAL |
| Sewer | 5/29/2026 | Not Ready for Inspection | ARAM AVEDISIAN |