768 N HARTZELL ST 90272

Certificate Information: 768 N HARTZELL ST 90272

Application / Permit
25010-30000-02295
Plan Check / Job No.
B25WL04287
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
Permit Issued
Issued on 9/12/2025
Issuing Office
Current Status
Issued on 9/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 KHEDER ALRAZAA
Corrections Issued 6/6/2025 KHEDER ALRAZAA
Quality Review Completed 6/6/2025 KEN GILL
Building Plans Picked Up 6/13/2025 APPLICANT
Applicant returned to address corrections 8/8/2025 KHEDER ALRAZAA
Plan Check Approved 9/12/2025 KHEDER ALRAZAA
Issued 9/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/11/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/11/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 6/11/2025 SARAH YOUSSEF
Grading Pre-Inspection Cleared 7/1/2025 LANNY MERRICK
Senate Bill 9 Cleared 7/25/2025 DALIA MOKAYED
Address approval Cleared 8/19/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/19/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/19/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 8/27/2025 LAVEON RIDER
GPI Written Notices Cleared 9/3/2025 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 9/3/2025 KHEDER ALRAZAA
Permit Cleared 9/3/2025 ERIK BEASLEY
Trees in Parkway Cleared 9/4/2025 RICHARD SANCHEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor R S C Construction Inc; Lic. No.: 1059714-B 3617 W 107TH STREET      INGLEWOOD, CA 90303
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 10/6/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/14/2025 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/15/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 10/23/2025 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 1/20/2026 Partial Approval HERBERT GIRON
Deputy Wood Construction 1/21/2026 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Rough 1/26/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/11/2026 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/26/2026 Approved DANIEL VERA
HVAC-Rough 2/26/2026 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/3/2026 Conditional Approval MICHAEL ALLEN
Green Building Rough 3/3/2026 Conditional Approval MICHAEL ALLEN
HVAC-Rough 3/3/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/3/2026 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 3/10/2026 Conditional Approval HERBERT GIRON
Green Building Rough 3/10/2026 Approved HERBERT GIRON
Insulation 3/10/2026 Approved HERBERT GIRON
Interior/Exterior Lathing 3/10/2026 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 3/10/2026 Approved HERBERT GIRON
Sewer 3/26/2026 Approved DANIEL VERA
Drywall Nailing 3/27/2026 Approved TEMISTOCLES CAAL
Shower Pan 4/24/2026 Approved TEMISTOCLES CAAL
Sewer 4/29/2026 Approved EVAN COOPER