15201 W MCKENDREE AVE 90272

Certificate Information: 15201 W MCKENDREE AVE 90272

Application / Permit
25010-30000-02132
Plan Check / Job No.
B25WL04004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2025 APPLICANT
Assigned to Plan Check Engineer 5/16/2025 RAPHAEL ROSAS
Corrections Issued 5/22/2025 RAPHAEL ROSAS
Quality Review Completed 5/22/2025 STEVEN KIM
Building Plans Picked Up 5/23/2025 APPLICANT
Plan Check Approved 7/7/2025 RAPHAEL ROSAS
Issued 7/7/2025 APPLICANT
CofO in Progress 4/9/2026 TEMISTOCLES CAAL
Permit Finaled 4/9/2026 RICHARD STEINBACH
CofO Issued 4/9/2026 RICHARD STEINBACH
Permit Finaled 4/9/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/10/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/10/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/10/2025 SAFA JAVANMARDI
Low Impact Development (LID) Cleared 6/17/2025 SARAH YOUSSEF
Hydrant and Access approval Cleared 6/24/2025 JERRY KAO
Roof/Waste drainage to street Cleared 6/26/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/5/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 8/13/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 8/25/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 8/25/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 12/4/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 12/10/2025 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 12/17/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 12/17/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 12/17/2025 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 12/19/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 12/19/2025 Partial Approval STEPHANIE SWANSON
Green Building Rough 12/19/2025 Approved STEPHANIE SWANSON
HVAC-Rough 12/19/2025 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 12/19/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 12/22/2025 Approved STEPHANIE SWANSON
Insulation 12/26/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 12/31/2025 Approved DANIEL VERA
Gas Test 1/12/2026 Approved TEMISTOCLES CAAL
Shower Pan 1/12/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/21/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/13/2026 Approved TEMISTOCLES CAAL
Gas Test 2/13/2026 Approved TEMISTOCLES CAAL
HVAC-Final 2/13/2026 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 2/13/2026 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 2/13/2026 Approved TEMISTOCLES CAAL
Final 2/25/2026 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 2/25/2026 Approved TEMISTOCLES CAAL
Green Building Final 2/25/2026 Approved TEMISTOCLES CAAL
HVAC-Final 2/25/2026 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 2/25/2026 Approved TEMISTOCLES CAAL
Final 4/7/2026 OK to Issue CofO TEMISTOCLES CAAL