15201 W MCKENDREE AVE 90272
Certificate Information: 15201 W MCKENDREE AVE 90272
- Application / Permit
- 25010-30000-02132
- Plan Check / Job No.
- B25WL04004
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2025 | RAPHAEL ROSAS |
| Corrections Issued | 5/22/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 5/22/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/23/2025 | APPLICANT |
| Plan Check Approved | 7/7/2025 | RAPHAEL ROSAS |
| Issued | 7/7/2025 | APPLICANT |
| CofO in Progress | 4/9/2026 | TEMISTOCLES CAAL |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
| CofO Issued | 4/9/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/10/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 6/17/2025 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 6/24/2025 | JERRY KAO |
| Roof/Waste drainage to street | Cleared | 6/26/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/13/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 8/25/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 12/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/10/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/17/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 12/17/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 12/17/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 12/19/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/19/2025 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 12/19/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 12/19/2025 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 12/19/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/22/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 12/26/2025 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 12/31/2025 | Approved | DANIEL VERA |
| Gas Test | 1/12/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/12/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/21/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/13/2026 | Approved | TEMISTOCLES CAAL |
| Gas Test | 2/13/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/13/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/13/2026 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 2/13/2026 | Approved | TEMISTOCLES CAAL |
| Final | 2/25/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/25/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 2/25/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/25/2026 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/25/2026 | Approved | TEMISTOCLES CAAL |
| Final | 4/7/2026 | OK to Issue CofO | TEMISTOCLES CAAL |