14742 W MCKENDREE AVE 90272

Certificate Information: 14742 W MCKENDREE AVE 90272

Application / Permit
25010-30000-02015
Plan Check / Job No.
B25WL03782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/13/2025 SERGIO SILVA
Corrections Issued 5/21/2025 SERGIO SILVA
Quality Review Completed 5/21/2025 CHIHARU SUZUKI
Building Plans Picked Up 5/22/2025 APPLICANT
Applicant returned to address corrections 6/2/2025 SERGIO SILVA
Applicant returned to address corrections 6/18/2025 SERGIO SILVA
Plan Check Approved 6/25/2025 SERGIO SILVA
Issued 6/25/2025 APPLICANT
CofO in Progress 5/29/2026 JUAN VALENZUELA
Permit Finaled 5/29/2026 RICHARD STEINBACH
CofO Issued 5/29/2026 RICHARD STEINBACH
Permit Finaled 5/29/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/9/2025 VISHAL MANDALIA
Eng Process Fee Ord 176,300 Cleared 6/9/2025 VISHAL MANDALIA
Sewer availability Cleared 6/9/2025 VISHAL MANDALIA
Construction near power lines Cleared 6/16/2025 RIDWAN HARDY
Low Impact Development (LID) Cleared 6/18/2025 SARAH YOUSSEF
Permit Cleared 6/18/2025 CINDY QI
Roof/Waste drainage to street Cleared 6/18/2025 CINDY QI
Hydrant and Access approval Cleared 6/25/2025 PATRICK PEREZ

Contact Information

Contractor South Coast Construction And Development; Lic. No.: 1000004-B 6380 WILSSHIRE BLVD # 1606      LOS ANGELES, CA 90048
Engineer Clayton,, Andrew; Lic. No.: C85452 1545 VICTORY BLVD   SUITE 102    GLENDALE, CA 91201
Engineer Grabarek,, Jaroslaw; Lic. No.: L9258 668 TWIN PEAKS AVE      SIMI VALLEY, CA 93065

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/30/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/5/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/5/2025 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/6/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 8/13/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval TEMISTOCLES CAAL
Insulation 8/19/2025 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 8/19/2025 Partial Approval TEMISTOCLES CAAL
Masonry Wall/Backfill 8/22/2025 Partial Approval STEPHANIE SWANSON
Special/Order Compliance 8/22/2025 Corrections Issued STEPHANIE SWANSON
Masonry Wall/Backfill 8/25/2025 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 9/10/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval TEMISTOCLES CAAL
Insulation 9/16/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 10/31/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 10/31/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 10/31/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Approved TEMISTOCLES CAAL
Green Building Rough 11/19/2025 Not Ready for Inspection TEMISTOCLES CAAL
Shower Pan 11/19/2025 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 11/19/2025 Not Ready for Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/25/2025 Approved STEPHANIE SWANSON
Green Building Rough 11/25/2025 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 11/25/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/26/2025 Not Ready for Inspection RUBEN RIVAS
Insulation 12/1/2025 Conditional Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 12/1/2025 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 12/8/2025 Approved HERBERT GIRON
Insulation 12/8/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 1/15/2026 Approved TEMISTOCLES CAAL
Sewer 3/16/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 3/16/2026 Approved TEMISTOCLES CAAL
Gas Test 3/25/2026 Corrections Issued MICHAEL ALLEN
Gas Test 4/9/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/7/2026 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 5/7/2026 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Final 5/14/2026 Approved JESUS PINEDA
Green Building Final 5/14/2026 Corrections Issued JESUS PINEDA
HVAC-Final 5/14/2026 Approved JESUS PINEDA
Final 5/19/2026 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 5/19/2026 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 5/19/2026 Not Ready for Inspection TEMISTOCLES CAAL
Smoke Detectors 5/19/2026 Approved TEMISTOCLES CAAL
Final 5/28/2026 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 5/28/2026 Approved TEMISTOCLES CAAL
Service/Power Release 5/28/2026 Approved TEMISTOCLES CAAL