711 N HAVERFORD AVE 90272

Certificate Information: 711 N HAVERFORD AVE 90272

Application / Permit
25010-30000-01998
Plan Check / Job No.
B25WL03732
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/29/2025
Issuing Office
Current Status
Issued on 8/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/11/2025 KEVIN MORALES
Corrections Issued 5/14/2025 KEVIN MORALES
Quality Review Completed 5/14/2025 EUGENE BARBEAU
Applicant returned to address corrections 7/3/2025 KEVIN MORALES
Plan Check Approved 7/22/2025 KEVIN MORALES
Issued 8/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/4/2025 VISHAL MANDALIA
Sewer availability Cleared 6/4/2025 VISHAL MANDALIA
Roof/Waste drainage to street Cleared 6/11/2025 CINDY QI
Hydrant and Access approval Cleared 6/12/2025 RUEL COLE

Contact Information

Contractor Gleicher Associates Inc; Lic. No.: 759307-B 415 SOUTH TOPANGA CANYON BLVD      TOPANGA, CA 90290

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/22/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 10/3/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/5/2025 Partial Approval STEPHANIE SWANSON
Deputy Reinf. Concrete 11/6/2025 No Access for Inspection KENNETH NAGLE
Deputy Drilled-In Anchors 12/2/2025 Conditional Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/4/2025 Partial Approval STEPHANIE SWANSON
Underground Mechanical 12/17/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/26/2025 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 1/22/2026 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 1/26/2026 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Conditional Approval HERBERT GIRON
Green Building Rough 2/6/2026 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 2/6/2026 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/1/2026 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 5/1/2026 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 5/15/2026 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/1/2026 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 6/1/2026 Corrections Issued MICHAEL ALLEN
Green Building Rough 6/1/2026 No Access for Inspection MICHAEL ALLEN
Verify Sprinkler Sign Off 6/1/2026 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 6/17/2026 Corrections Issued ARAM AVEDISIAN
Pre-Inspection 6/17/2026 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/22/2026 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 7/22/2026 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 7/22/2026 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 7/22/2026 Approved STEPHANIE SWANSON