- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED 1 CAR GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Current Status
- Issued on 3/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2025 | SERGIO SILVA |
| Corrections Issued | 4/30/2025 | SERGIO SILVA |
| Quality Review Completed | 4/30/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 5/6/2025 | APPLICANT |
| Applicant returned to address corrections | 9/19/2025 | SERGIO SILVA |
| Applicant returned to address corrections | 9/22/2025 | SERGIO SILVA |
| Plan Check Approved | 11/20/2025 | SERGIO SILVA |
| Issued | 3/3/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | VISHAL MANDALIA |
| Sewer availability | Cleared | 6/4/2025 | VISHAL MANDALIA |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 9/25/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Pb3 Construction; Lic. No.: 1129086-B | 6605 JOSHUA LANE SAN BERNARDINO, CA 92407 |
| Engineer | Nastarin,, Hooman; Lic. No.: C62199 | 554 S SAN VICNETE BLVD 202 LOS ANGELES, CA 90048 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 7/24/2026 |
| Verify Sprinkler Sign Off | 7/24/2026 |
| Green Building Rough | 7/24/2026 |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2026 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 3/23/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/23/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/3/2026 | No Access for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/10/2026 | Approved | STEPHANIE SWANSON |
| Wood Frame | 4/28/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/6/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2026 | Partial Approval | STEPHANIE SWANSON |