930 N EMBURY ST 90272
Certificate Information: 930 N EMBURY ST 90272
- Application / Permit
- 25010-30000-01680
- Plan Check / Job No.
- B25WL03212
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- Issued on 6/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2025 | SERGIO SILVA |
| Corrections Issued | 5/2/2025 | SERGIO SILVA |
| Quality Review Completed | 5/5/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/21/2025 | SERGIO SILVA |
| Applicant returned to address corrections | 6/2/2025 | SERGIO SILVA |
| Plan Check Approved | 6/16/2025 | SERGIO SILVA |
| Issued | 6/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 5/7/2025 | MITESH PATEL |
| Permit | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/7/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2025 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 5/13/2025 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | SAFA JAVANMARDI |
| GPI Written Notices | Cleared | 6/2/2025 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 6/2/2025 | LANNY MERRICK |
| Trees in Parkway | Cleared | 6/5/2025 | BRANDON WONG |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 1816 HILLCREST AVENUE GLENDALE, CA 91202 |
| Contractor | R S C Construction Inc; Lic. No.: 1059714-B | 3617 W 107TH STREET INGLEWOOD, CA 90303 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/14/2025 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 7/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/17/2025 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 7/21/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 7/25/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 9/12/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 10/10/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 10/31/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/31/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/4/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/4/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/21/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 12/1/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 1/29/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/5/2026 | Approved | TEMISTOCLES CAAL |
| Sewer | 3/26/2026 | Approved | TEMISTOCLES CAAL |