814 N HARTZELL ST 90272
Certificate Information: 814 N HARTZELL ST 90272
- Application / Permit
- 25010-30000-01637
- Plan Check / Job No.
- B25WL03127
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | JOHNNY WU |
| Corrections Issued | 4/30/2025 | JOHNNY WU |
| Quality Review Completed | 5/6/2025 | KEN GILL |
| Building Plans Picked Up | 5/9/2025 | APPLICANT |
| Applicant returned to address corrections | 5/28/2025 | JOHNNY WU |
| Applicant returned to address corrections | 5/29/2025 | JOHNNY WU |
| Plan Check Approved | 5/29/2025 | JOHNNY WU |
| Issued | 6/2/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 4/30/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/30/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 5/6/2025 | PATRICK PEREZ |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Dolan Design & Build, Lcc; Lic. No.: 1135363-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Underground Mechanical | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 6/6/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/24/2025 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/30/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 9/3/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/4/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/10/2025 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 9/11/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | KENNETH NAGLE |
| Deputy Wood Construction | 9/17/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 9/23/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/23/2025 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 9/23/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/8/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/23/2025 | Approved | KENNETH NAGLE |
| Shower Pan | 10/29/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 11/5/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 11/19/2025 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 4/8/2026 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 4/14/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Underground Mechanical | 4/15/2026 | Approved | TEMISTOCLES CAAL |