1130 N ILIFF ST 90272

Certificate Information: 1130 N ILIFF ST 90272

Application / Permit
25010-30000-01325
Plan Check / Job No.
B25WL02488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT .
Permit Issued
Issued on 9/23/2025
Issuing Office
Current Status
Issued on 9/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/28/2025 APPLICANT
Assigned to Plan Check Engineer 4/1/2025 RAPHAEL ROSAS
Corrections Issued 4/4/2025 RAPHAEL ROSAS
Quality Review Completed 4/8/2025 STEVEN KIM
Building Plans Picked Up 4/9/2025 APPLICANT
Applicant returned to address corrections 5/27/2025 RAPHAEL ROSAS
Applicant returned to address corrections 7/11/2025 RAPHAEL ROSAS
Applicant returned to address corrections 9/2/2025 RAPHAEL ROSAS
Plan Check Approved 9/23/2025 RAPHAEL ROSAS
Issued 9/23/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/8/2025 VISHAL MANDALIA
Eng Process Fee Ord 176,300 Cleared 4/9/2025 VISHAL MANDALIA
Low Impact Development (LID) Cleared 4/10/2025 MITESH PATEL
Roof/Waste drainage to street Cleared 4/10/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 4/11/2025 PATRICK PEREZ

Contact Information

Contractor G C Aquascape; Lic. No.: 711587-B 1903 CALIFORNIA AVENUE      SANTA MONICA, CA 90403
Engineer Masterman,, Gary Clyde; Lic. No.: GE567 1766 EAGLE RIDGE CIR      WICHITA FALLS, TX 76309
Engineer Southerland,, Richard Charles; Lic. No.: C88965 2335 E COLORADO BLVD   SUITE 115, # 170    PASADENA, CA 91107

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2025 Partial Inspection TEMISTOCLES CAAL
Pre-Inspection 11/10/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 11/24/2025 Partial Approval KENNETH NAGLE
PLUMBING-Rough 11/24/2025 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 12/1/2025 No Access for Inspection KENNETH NAGLE
Reinforced Concrete Frame 12/10/2025 Not Ready for Inspection TEMISTOCLES CAAL
Structural Steel Frame 12/10/2025 Not Ready for Inspection TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 12/17/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 2/9/2026 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Rough 2/9/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 2/11/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/13/2026 Not Ready for Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 3/6/2026 Partial Approval TEMISTOCLES CAAL
Deputy Drilled-In Anchors 3/9/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/20/2026 Partial Approval RYAN SALAZAR
Deputy Reinf. Concrete 3/23/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/3/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 4/6/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/9/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Partial Approval TEMISTOCLES CAAL