1130 N ILIFF ST 90272
Certificate Information: 1130 N ILIFF ST 90272
- Application / Permit
- 25010-30000-01325
- Plan Check / Job No.
- B25WL02488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT .
- Permit Issued
- Issued on 9/23/2025
- Issuing Office
- Current Status
- Issued on 9/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2025 | RAPHAEL ROSAS |
| Corrections Issued | 4/4/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/8/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/9/2025 | APPLICANT |
| Applicant returned to address corrections | 5/27/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/11/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/2/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 9/23/2025 | RAPHAEL ROSAS |
| Issued | 9/23/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/8/2025 | VISHAL MANDALIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2025 | VISHAL MANDALIA |
| Low Impact Development (LID) | Cleared | 4/10/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/10/2025 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 4/11/2025 | PATRICK PEREZ |
Contact Information
| Contractor | G C Aquascape; Lic. No.: 711587-B | 1903 CALIFORNIA AVENUE SANTA MONICA, CA 90403 |
| Engineer | Masterman,, Gary Clyde; Lic. No.: GE567 | 1766 EAGLE RIDGE CIR WICHITA FALLS, TX 76309 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Pre-Inspection | 11/10/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/24/2025 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 11/24/2025 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 12/1/2025 | No Access for Inspection | KENNETH NAGLE |
| Reinforced Concrete Frame | 12/10/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Structural Steel Frame | 12/10/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/9/2026 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/9/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 2/11/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/13/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/6/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 3/9/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/20/2026 | Partial Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 3/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 4/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/9/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2026 | Partial Approval | TEMISTOCLES CAAL |