1419 N MONTE GRANDE PL 90272

Certificate Information: 1419 N MONTE GRANDE PL 90272

Application / Permit
25010-30000-01136
Plan Check / Job No.
B25WL02063
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/15/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2025 APPLICANT
Assigned to Plan Check Engineer 3/18/2025 SERGIO SILVA
Corrections Issued 3/27/2025 SERGIO SILVA
Quality Review Completed 3/27/2025 CHIHARU SUZUKI
Building Plans Picked Up 3/28/2025 APPLICANT
Applicant returned to address corrections 4/7/2025 SERGIO SILVA
Applicant returned to address corrections 4/16/2025 SERGIO SILVA
Plan Check Approved 4/24/2025 SERGIO SILVA
Issued 5/15/2025 APPLICANT
CofO in Progress 7/2/2026 JUAN VALENZUELA
Permit Finaled 7/2/2026 JUAN VALENZUELA
CofO Issued 7/2/2026 JUAN VALENZUELA
Permit Finaled 7/2/2026 JUAN VALENZUELA

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/28/2025 VISHAL MANDALIA
Hydrant and Access approval Cleared 4/5/2025 PATRICK PEREZ
Distance to fire station Cleared 4/8/2025 PATRICK PEREZ
Eng Process Fee Ord 176,300 Cleared 4/16/2025 VISHAL MANDALIA
Permit Cleared 4/16/2025 VISHAL MANDALIA
Sewer availability Cleared 4/16/2025 VISHAL MANDALIA
Low Impact Development (LID) Cleared 5/8/2025 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/9/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Sweeney,, Patrick; Lic. No.: C89421 4760 ANDALUSIA AVE      SAN DIEGO, CA 92117

Inspector Information

MICHAEL ALLEN, (310) 914-3886 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/16/2025 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 7/7/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 7/9/2025 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 7/28/2025 Approved BOBBY KEY
Footing/Foundation/Slab 7/28/2025 Approved BOBBY KEY
Deputy Reinf. Concrete 7/29/2025 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Conditional Approval BOBBY KEY
PLUMBING-Rough 12/11/2025 Corrections Issued BOBBY KEY
HVAC-Rough 12/22/2025 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 12/30/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 1/2/2026 Conditional Approval BOBBY KEY
HVAC-Rough 1/2/2026 Approved BOBBY KEY
PLUMBING-Rough 1/2/2026 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 1/14/2026 Corrections Issued BOBBY KEY
PLUMBING-Rough 1/14/2026 Approved BOBBY KEY
Interior/Exterior Lathing 1/26/2026 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 1/28/2026 Corrections Issued DANIEL VERA
Verify Sprinkler Sign Off 1/28/2026 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 2/12/2026 Approved DANIEL VERA
Verify Sprinkler Sign Off 2/12/2026 Approved DANIEL VERA
Insulation 2/17/2026 Approved DANIEL VERA
Drywall Nailing 2/23/2026 Approved DANIEL VERA
Interior/Exterior Lathing 3/19/2026 Approved DANIEL VERA
Interior/Exterior Lathing 3/20/2026 Approved DANIEL VERA
Shower Pan 3/20/2026 Approved DANIEL VERA
Underground Mechanical 4/28/2026 Approved DANIEL VERA
Sewer 5/6/2026 Not Ready for Inspection DANIEL VERA
Gas Test 5/15/2026 Approved MICHAEL ALLEN
Service/Power Release 5/15/2026 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 6/1/2026 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/1/2026 Corrections Issued MICHAEL ALLEN
Service/Power Release 6/1/2026 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 6/3/2026 Approved MICHAEL ALLEN
HVAC-Final 6/3/2026 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Final 6/3/2026 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 6/8/2026 Approved MICHAEL ALLEN
Gas Test 6/8/2026 Approved MICHAEL ALLEN
HVAC-Final 6/8/2026 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Final 6/8/2026 Approved MICHAEL ALLEN
Gas Test 6/10/2026 Approved MICHAEL ALLEN
Service/Power Release 6/10/2026 Approved MICHAEL ALLEN
Final 6/18/2026 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/18/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/18/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/18/2026 Approved MICHAEL ALLEN
Final 7/2/2026 OK to Issue CofO JUAN VALENZUELA