1419 N MONTE GRANDE PL 90272
Certificate Information: 1419 N MONTE GRANDE PL 90272
- Application / Permit
- 25010-30000-01136
- Plan Check / Job No.
- B25WL02063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2025 | SERGIO SILVA |
| Corrections Issued | 3/27/2025 | SERGIO SILVA |
| Quality Review Completed | 3/27/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/28/2025 | APPLICANT |
| Applicant returned to address corrections | 4/7/2025 | SERGIO SILVA |
| Applicant returned to address corrections | 4/16/2025 | SERGIO SILVA |
| Plan Check Approved | 4/24/2025 | SERGIO SILVA |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 7/2/2026 | JUAN VALENZUELA |
| Permit Finaled | 7/2/2026 | JUAN VALENZUELA |
| CofO Issued | 7/2/2026 | JUAN VALENZUELA |
| Permit Finaled | 7/2/2026 | JUAN VALENZUELA |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/28/2025 | VISHAL MANDALIA |
| Hydrant and Access approval | Cleared | 4/5/2025 | PATRICK PEREZ |
| Distance to fire station | Cleared | 4/8/2025 | PATRICK PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2025 | VISHAL MANDALIA |
| Permit | Cleared | 4/16/2025 | VISHAL MANDALIA |
| Sewer availability | Cleared | 4/16/2025 | VISHAL MANDALIA |
| Low Impact Development (LID) | Cleared | 5/8/2025 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/9/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sweeney,, Patrick; Lic. No.: C89421 | 4760 ANDALUSIA AVE SAN DIEGO, CA 92117 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2025 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 7/7/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 7/9/2025 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 7/28/2025 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 7/29/2025 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 12/11/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 12/22/2025 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 12/30/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 1/2/2026 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 1/2/2026 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/2/2026 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 1/14/2026 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/14/2026 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/26/2026 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 1/28/2026 | Corrections Issued | DANIEL VERA |
| Verify Sprinkler Sign Off | 1/28/2026 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 2/12/2026 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 2/12/2026 | Approved | DANIEL VERA |
| Insulation | 2/17/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 2/23/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/19/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/20/2026 | Approved | DANIEL VERA |
| Shower Pan | 3/20/2026 | Approved | DANIEL VERA |
| Underground Mechanical | 4/28/2026 | Approved | DANIEL VERA |
| Sewer | 5/6/2026 | Not Ready for Inspection | DANIEL VERA |
| Gas Test | 5/15/2026 | Approved | MICHAEL ALLEN |
| Service/Power Release | 5/15/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/1/2026 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 6/1/2026 | Corrections Issued | MICHAEL ALLEN |
| Service/Power Release | 6/1/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/3/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 6/3/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Final | 6/3/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/8/2026 | Approved | MICHAEL ALLEN |
| Gas Test | 6/8/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 6/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Final | 6/8/2026 | Approved | MICHAEL ALLEN |
| Gas Test | 6/10/2026 | Approved | MICHAEL ALLEN |
| Service/Power Release | 6/10/2026 | Approved | MICHAEL ALLEN |
| Final | 6/18/2026 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 6/18/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 6/18/2026 | Approved | MICHAEL ALLEN |
| Final | 7/2/2026 | OK to Issue CofO | JUAN VALENZUELA |