951 N EMBURY ST 90272
Certificate Information: 951 N EMBURY ST 90272
- Application / Permit
- 25010-30000-01102
- Plan Check / Job No.
- B25WL02023
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 27'-6" x 82'-1". NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2025 | SERGIO SILVA |
| Corrections Issued | 3/24/2025 | SERGIO SILVA |
| Quality Review Completed | 3/24/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/25/2025 | APPLICANT |
| Applicant returned to address corrections | 4/2/2025 | SERGIO SILVA |
| Plan Check Approved | 5/7/2025 | SERGIO SILVA |
| Issued | 5/8/2025 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 3/23/2025 | VISHAL MANDALIA |
| Sewer availability | Cleared | 3/23/2025 | VISHAL MANDALIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2025 | VISHAL MANDALIA |
| Low Impact Development (LID) | Cleared | 3/25/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/25/2025 | VISHAL MANDALIA |
| Trees in Parkway | Cleared | 3/25/2025 | MIGUEL ORNELAS |
| Hydrant and Access approval | Cleared | 3/26/2025 | JERRY KAO |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Smoke Detectors | 6/10/2026 |
| Final | 6/10/2026 |
Inspection Request History
| Special/Order Compliance | 5/13/2025 | Partial Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | BOBBY KEY |
| Sewer | 7/14/2025 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/29/2025 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 7/31/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 9/24/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 9/24/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 10/1/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/7/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/21/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 10/28/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/28/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/10/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Pre-Stress Concrete | 12/9/2025 | No Access for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 12/9/2025 | Approved | DANIEL VERA |
| Shower Pan | 12/9/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 12/11/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 3/11/2026 | Approved | TEMISTOCLES CAAL |
| Gas Test | 3/18/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/18/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | MICHAEL ALLEN |
| Service/Power Release | 3/27/2026 | Approved | JUAN VALENZUELA |
| HVAC-Final | 5/26/2026 | Approved | JESUS PINEDA |
| Final | 6/4/2026 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 6/4/2026 | Not Ready for Inspection | JESUS PINEDA |