15034 W MCKENDREE AVE 90272
Certificate Information: 15034 W MCKENDREE AVE 90272
- Application / Permit
- 25010-30000-01071
- Plan Check / Job No.
- B25WL01929
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | SERGIO SILVA |
| Corrections Issued | 3/19/2025 | SERGIO SILVA |
| Quality Review Completed | 3/19/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/20/2025 | APPLICANT |
| Applicant returned to address corrections | 4/28/2025 | SERGIO SILVA |
| Plan Check Approved | 5/12/2025 | CHIHARU SUZUKI |
| Issued | 5/12/2025 | APPLICANT |
| CofO in Progress | 2/17/2026 | TEMISTOCLES CAAL |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/31/2025 | PATRICK PEREZ |
| BHO/Hillside ordinance | Cleared | 4/1/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/1/2025 | DAVID LOPEZ |
| Distance to fire station | Cleared | 4/2/2025 | PATRICK PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 4/4/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/9/2025 | DAVID LOPEZ |
| Permit | Cleared | 4/18/2025 | DAVID PEREZ |
| Trees in Parkway | Cleared | 4/18/2025 | MIGUEL ORNELAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shirley,, Peter; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 5/21/2025 | No Access for Inspection | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 6/4/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/10/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/10/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Steel/Welding | 7/11/2025 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Conditional Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 9/19/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/24/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 9/25/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/25/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 9/26/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 9/26/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/26/2025 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 9/26/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/1/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 10/7/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/21/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 11/21/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/12/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/12/2026 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 1/12/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 1/15/2026 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 1/15/2026 | Approved | JUAN VALENZUELA |
| Service/Power Release | 1/15/2026 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 1/20/2026 | Approved | TEMISTOCLES CAAL |
| Final | 2/6/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/6/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 2/6/2026 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Approved | TEMISTOCLES CAAL |
| Final | 2/17/2026 | OK to Issue CofO | TEMISTOCLES CAAL |