15256 W DE PAUW ST 90272
Certificate Information: 15256 W DE PAUW ST 90272
- Application / Permit
- 25010-30000-00629
- Plan Check / Job No.
- B25WL01021
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2025 | SERGIO SILVA |
| Corrections Issued | 2/13/2025 | SERGIO SILVA |
| Quality Review Completed | 2/14/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/24/2025 | APPLICANT |
| Plan Check Approved | 3/5/2025 | SERGIO SILVA |
| Issued | 3/7/2025 | APPLICANT |
| CofO in Progress | 7/23/2026 | STEPHANIE SWANSON |
| Permit Finaled | 7/23/2026 | RICHARD STEINBACH |
| CofO Issued | 7/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 7/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2025 | DARIN LAM |
| Low Impact Development | Cleared | 2/22/2025 | MARTIN FRAGOSO |
| Permit | Cleared | 2/22/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 2/22/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/22/2025 | DARIN LAM |
| Trees in Parkway | Cleared | 2/22/2025 | MIGUEL ORNELAS |
| Hydrant and Access approval | Cleared | 3/1/2025 | LAVEON RIDER |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | D'Arco Inc; Lic. No.: 1035898-B | P O BOX 4425 SUNLAND, CA 91041 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2025 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 4/14/2025 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 4/18/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/18/2025 | Approved | BOBBY KEY |
| Deputy Wood Construction | 5/1/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 5/16/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/10/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/15/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 7/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 7/24/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 7/24/2025 | Approved | STEPHANIE SWANSON |
| Shower Pan | 7/24/2025 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 7/24/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/7/2025 | Approved | BOBBY KEY |
| Green Building Rough | 8/7/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/7/2025 | Partial Approval | BOBBY KEY |
| Insulation | 8/19/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 8/26/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/26/2025 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 9/9/2025 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 4/2/2026 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/1/2026 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 5/1/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 5/26/2026 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/1/2026 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 7/1/2026 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 7/9/2026 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 7/9/2026 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/14/2026 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 7/16/2026 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 7/16/2026 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2026 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 7/16/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 7/16/2026 | Approved | STEPHANIE SWANSON |
| Final | 7/23/2026 | OK to Issue CofO | STEPHANIE SWANSON |
| Service/Power Release | 7/23/2026 | Approved | STEPHANIE SWANSON |