9107 W BEVERLYWOOD ST 90034
Certificate Information: 9107 W BEVERLYWOOD ST 90034
- Application / Permit
- 25010-30000-00517
- Plan Check / Job No.
- B25WL00800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH ATTACHED GARAGE ---1 OF 3---
- Permit Issued
- Issued on 5/27/2025
- Issuing Office
- Current Status
- Issued on 5/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | BEHROUZ KHOKHAR |
| Corrections Issued | 2/20/2025 | BEHROUZ KHOKHAR |
| Quality Review Completed | 2/28/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/3/2025 | APPLICANT |
| Applicant returned to address corrections | 3/25/2025 | BEHROUZ KHOKHAR |
| Plan Check Approved | 5/27/2025 | BEHROUZ KHOKHAR |
| Issued | 5/27/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/27/2025 | JERRY KAO |
| Address approval | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 3/4/2025 | BRANDON WONG |
| Permit | Cleared | 3/8/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/10/2025 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 3/25/2025 | CHIHARU SUZUKI |
| Grading Pre-Inspection | Cleared | 3/25/2025 | BEHROUZ KHOKHAR |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Babic,, Rade; Lic. No.: M38573 | 58 CLARET IRVINE, CA 92614 |
| Engineer | Chrysostomo,, Anderson; Lic. No.: L9216 | 9592 ERSKINE DRIVE HUNTINGTON BEACH, CA 92646 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | Waddell,, Ian R; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/2/2025 | Partial Approval | EVAN COOPER |
| Deputy Pre-Stress Concrete | 12/9/2025 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 12/11/2025 | Approved | EVAN COOPER |
| METHANE-Barrier | 12/11/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 12/11/2025 | Approved | EVAN COOPER |
| Pre-Inspection | 12/11/2025 | Approved | EVAN COOPER |
| Deputy Pre-Stress Concrete | 12/15/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Partial Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 1/27/2026 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Approved | WILBER ROSALES |
| HVAC-Rough | 2/12/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 2/12/2026 | Approved | WILBER ROSALES |
| Pre-Inspection | 2/27/2026 | Partial Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 3/9/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 3/9/2026 | Approved | WILBER ROSALES |
| METHANE-Rough | 3/9/2026 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | WILBER ROSALES |
| Insulation | 3/24/2026 | Not Ready for Inspection | WILBER ROSALES |
| Insulation | 3/25/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 3/25/2026 | Partial Approval | WILBER ROSALES |
| Drywall Nailing | 4/3/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/3/2026 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 4/29/2026 | Approved | WILBER ROSALES |
| Shower Pan | 4/29/2026 | Approved | WILBER ROSALES |
| Underground Mechanical | 5/27/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/2/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 7/2/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 7/2/2026 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 7/2/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 7/14/2026 | Approved | BOBBY KEY |
| Grading Pre-Inspection | 7/23/2026 | No Result Entered | WILBER ROSALES |
| HVAC-Final | 7/23/2026 | No Result Entered | WILBER ROSALES |
| Service/Power Release | 7/23/2026 | No Result Entered | WILBER ROSALES |