10507 W WILKINS AVE 90024

Certificate Information: 10507 W WILKINS AVE 90024

Application / Permit
25010-30000-00514
Plan Check / Job No.
B25WL00796
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1 STORY DET. ADU Per GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (d) ---2 OF 4---
Permit Issued
Issued on 6/13/2025
Issuing Office
Current Status
Issued on 6/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 ZENA HADDIS
Corrections Issued 2/28/2025 ZENA HADDIS
Quality Review Completed 3/4/2025 CHIHARU SUZUKI
Building Plans Picked Up 3/14/2025 APPLICANT
Plan Check Approved 6/13/2025 ZENA HADDIS
Issued 6/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/1/2025 DARIN LAM
Roof/Waste drainage to street Cleared 3/1/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/3/2025 DARIN LAM
Sewer availability Cleared 3/3/2025 DARIN LAM
Construction near power lines Cleared 3/6/2025 ENRIQUE ACOSTA
Specific Plan Cleared 3/6/2025 HAMID GHAEMMAGHAMI
Permit Cleared 6/9/2025 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 6/12/2025 BRANDON WONG
GPI Written Notices Cleared 6/13/2025 ZENA HADDIS
Grading Pre-Inspection Cleared 6/13/2025 ZENA HADDIS

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 200      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 347 ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Nguyen,, Huan; Lic. No.: C64238 15 STUDEBAKER      IRVINE, CA 92618
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2025 Approved MICHAEL ALLEN
Sewer 11/3/2025 Approved MICHAEL ALLEN
Underground Mechanical 11/3/2025 Approved MICHAEL ALLEN
METHANE-Subgrade 11/7/2025 Approved STEPHANIE SWANSON
METHANE-Barrier 11/10/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 12/11/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 12/11/2025 Approved MICHAEL ALLEN
METHANE-Final 12/11/2025 Not Ready for Inspection MICHAEL ALLEN
Deputy Pre-Stress Concrete 12/16/2025 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Approved MICHAEL ALLEN
ELECTRICAL-Rough 2/25/2026 Approved RUBEN RIVAS
HVAC-Rough 2/25/2026 Partial Approval RUBEN RIVAS
PLUMBING-Rough 2/25/2026 Approved RUBEN RIVAS
HVAC-Rough 3/3/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 3/3/2026 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 3/24/2026 Approved WILBER ROSALES
Green Building Rough 3/24/2026 Approved WILBER ROSALES
Insulation 3/24/2026 Corrections Issued WILBER ROSALES
METHANE-Rough 3/24/2026 Approved WILBER ROSALES
Verify Sprinkler Sign Off 3/24/2026 Approved WILBER ROSALES
Drywall Nailing 4/2/2026 Approved MICHAEL ALLEN
Insulation 4/2/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 5/5/2026 Approved MICHAEL LEWIS
Shower Pan 5/5/2026 Approved MICHAEL LEWIS
Gas Test 6/3/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 6/15/2026 Corrections Issued ANTHONY EGSON
Service/Power Release 6/15/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 6/18/2026 Corrections Issued ASHLEY THOMPSON
Service/Power Release 6/18/2026 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 6/23/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Final 6/24/2026 Partial Approval ANTHONY EGSON
HVAC-Final 7/9/2026 Corrections Issued ARAM AVEDISIAN
Final 7/15/2026 Corrections Issued ANTHONY EGSON
Green Building Final 7/15/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/15/2026 SGSOV Approved ANTHONY EGSON
Service/Power Release 7/15/2026 Approved ANTHONY EGSON
Smoke Detectors 7/15/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 7/20/2026 Approved ANTHONY EGSON
Final 7/20/2026 Corrections Issued ANTHONY EGSON
HVAC-Final 7/20/2026 Approved ANTHONY EGSON