3602 S GRAND VIEW BLVD 90066

Certificate Information: 3602 S GRAND VIEW BLVD 90066

Application / Permit
25010-30000-00426
Plan Check / Job No.
B25WL00666
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new 2-story ADU with 1-car garage per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/28/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 KAVIAN REFAHI
Corrections Issued 2/19/2025 KAVIAN REFAHI
Quality Review Completed 2/27/2025 CHIHARU SUZUKI
Building Plans Picked Up 2/28/2025 APPLICANT
Plan Check Approved 5/23/2025 KAVIAN REFAHI
Issued 5/28/2025 APPLICANT
CofO in Progress 5/11/2026 MICHAEL LEWIS
No Progress 5/15/2026 MICHAEL LEWIS
CofO in Progress 5/15/2026 MICHAEL LEWIS
Permit Finaled 6/4/2026 RICHARD STEINBACH
CofO Issued 6/4/2026 RICHARD STEINBACH
Permit Finaled 6/4/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/20/2025 DARIN LAM
Roof/Waste drainage to street Cleared 3/20/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/26/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/26/2025 HISASHI KOBAYAKAWA
Specific Plan Cleared 4/1/2025 JOSHUA JONES
Hydrant and Access approval Cleared 4/22/2025 PATRICK PEREZ
Construction near power lines Cleared 4/23/2025 RIDWAN HARDY
GPI Written Notices Cleared 5/23/2025 KAVIAN REFAHI
Grading Pre-Inspection Cleared 5/23/2025 KAVIAN REFAHI

Contact Information

Architect Buttyan,, Anne Elisabeth; Lic. No.: C41601 1225 PRINCETON ST #C      SANTA MONICA, CA 90404
Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2025 Partial Approval WILBER ROSALES
PLUMBING-Rough 6/6/2025 Partial Approval WILBER ROSALES
Deputy Reinf. Concrete 6/9/2025 Conditional Approval WILBER ROSALES
Footing/Foundation/Slab 6/16/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Corrections Issued KIRK SANDERS
Green Building Rough 7/21/2025 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 7/21/2025 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval KIRK SANDERS
Green Building Rough 7/23/2025 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 7/23/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 8/27/2025 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Partial Approval EVAN COOPER
HVAC-Rough 8/27/2025 Corrections Issued EVAN COOPER
PLUMBING-Rough 8/27/2025 Corrections Issued EVAN COOPER
Rough-Elec/Plmb/HVAC 8/28/2025 Approved MICHAEL ALLEN
Special/Order Compliance 8/28/2025 Corrections Issued MICHAEL ALLEN
Wood Frame 8/28/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 9/11/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 9/11/2025 Partial Approval KIRK SANDERS
Shower Pan 9/11/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/15/2025 Approved MICHAEL ALLEN
Green Building Rough 9/15/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 9/15/2025 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 9/15/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 9/17/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 9/19/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 9/19/2025 Approved KIRK SANDERS
Insulation 9/19/2025 Approved KIRK SANDERS
Drywall Nailing 10/3/2025 Conditional Approval KIRK SANDERS
Drywall Nailing 10/9/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 10/9/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 1/22/2026 Corrections Issued MICHAEL ALLEN
Final 1/28/2026 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 1/28/2026 Approved ARAM AVEDISIAN
Green Building Final 1/28/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Required ARAM AVEDISIAN
Service/Power Release 1/28/2026 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 1/28/2026 Approved ARAM AVEDISIAN
Pre-Inspection 2/3/2026 Partial Inspection ARAM AVEDISIAN
Service/Power Release 2/13/2026 Approved ARAM AVEDISIAN
Final 3/24/2026 Partial Inspection ANTHONY EGSON
ELECTRICAL-Final 5/1/2026 Approved ANTHONY EGSON
Final 5/1/2026 Conditional Approval ANTHONY EGSON
HVAC-Final 5/1/2026 Approved ANTHONY EGSON
PLUMBING-Final 5/1/2026 Approved ANTHONY EGSON
Final 5/8/2026 OK to Issue CofO MICHAEL LEWIS