1416-1416 1/2 E PLEASANT AVE 90033

Certificate Information: 1416-1416 1/2 E PLEASANT AVE 90033

Application / Permit
25010-30000-00420
Plan Check / Job No.
B25WL00655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story Duplex with attached garage and storage at front of the lot
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
Issued on 5/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 REZA HAGHIGHAT
Corrections Issued 2/12/2025 REZA HAGHIGHAT
Quality Review Completed 2/18/2025 CHIHARU SUZUKI
Building Plans Picked Up 2/18/2025 APPLICANT
Disabled Access Plans Picked Up 3/26/2025 APPLICANT
Plan Check Approved 5/20/2025 REZA HAGHIGHAT
Issued 5/30/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/20/2025 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/21/2025 ERNEST TSE
Clean Up Green Up Cleared 2/25/2025 ROSALINDA MEZA
ZA Case Cleared 2/25/2025 ROSALINDA MEZA
ZA Case Cleared 2/25/2025 ROSALINDA MEZA
ZA Case Cleared 2/25/2025 ROSALINDA MEZA
ZA Case Cleared 2/25/2025 ROSALINDA MEZA
Trees in Parkway Cleared 3/3/2025 BRANDON WONG
Frnt yard landscape/Water mgmt Cleared 3/5/2025 ROSALINDA MEZA
ZI Cleared 3/5/2025 ROSALINDA MEZA
Address approval Cleared 3/11/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/19/2025 CELINA MORENO
Permit Cleared 3/19/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 3/19/2025 CELINA MORENO
Sewer availability Cleared 4/9/2025 CELINA MORENO
Highway dedication Cleared 4/28/2025 CELINA MORENO
GPI Written Notices Cleared 5/20/2025 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 5/20/2025 REZA HAGHIGHAT

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/25/2025 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 7/25/2025 Partial Approval FREDDIE RIVERA
Underground Mechanical 7/25/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 8/6/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 9/11/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval FREDDIE RIVERA
Deputy Wood Construction 9/17/2025 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Approved ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Partial Approval FREDDIE RIVERA
HVAC-Rough 2/25/2026 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 2/25/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/26/2026 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/26/2026 Approved FREDDIE RIVERA
Green Building Rough 2/26/2026 Approved FREDDIE RIVERA
MERV13>=Rough 2/26/2026 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/26/2026 Approved FREDDIE RIVERA
Insulation 3/4/2026 Approved JUSTIN HAWLEY
Drywall Nailing 3/13/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/13/2026 Partial Approval FREDDIE RIVERA
Sewer 6/18/2026 Approved FREDDIE RIVERA
Underground Mechanical 6/18/2026 Partial Approval FREDDIE RIVERA
Underground Mechanical 7/15/2026 Partial Approval JUSTIN HAWLEY