1412 1/2-3/4 E PLEASANT AVE 90033

Certificate Information: 1412 1/2-3/4 E PLEASANT AVE 90033

Application / Permit
25010-30000-00419
Plan Check / Job No.
B25WL00653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story Duplex with attached ADU at rear of the lot per LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
Issued on 5/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 REZA HAGHIGHAT
Corrections Issued 2/12/2025 REZA HAGHIGHAT
Quality Review Completed 2/18/2025 CHIHARU SUZUKI
Building Plans Picked Up 2/18/2025 APPLICANT
Disabled Access Plans Picked Up 3/26/2025 APPLICANT
Plan Check Approved 5/20/2025 REZA HAGHIGHAT
Issued 5/30/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/21/2025 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/25/2025 SARAH YOUSSEF
Trees in Parkway Cleared 3/3/2025 BRANDON WONG
Address approval Cleared 3/10/2025 CELINA MORENO
Clean Up Green Up Cleared 3/13/2025 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 3/13/2025 DANIEL CORONADO
ZA Case Cleared 3/13/2025 DANIEL CORONADO
ZA Case Cleared 3/13/2025 DANIEL CORONADO
ZA Case Cleared 3/13/2025 DANIEL CORONADO
ZA Case Cleared 3/13/2025 DANIEL CORONADO
ZI Cleared 3/13/2025 DANIEL CORONADO
Permit Cleared 3/19/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 3/19/2025 CELINA MORENO
Sewer availability Cleared 4/9/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/22/2025 CELINA MORENO
Highway dedication Cleared 4/30/2025 CELINA MORENO
DAS Clearance Cleared 5/14/2025 REZA HAGHIGHAT
GPI Written Notices Cleared 5/20/2025 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 5/20/2025 REZA HAGHIGHAT

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 10/22/2025 Partial Approval FREDDIE RIVERA
Deputy Reinf. Concrete 10/28/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 10/28/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/25/2025 Partial Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Corrections Issued ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 2/13/2026 Approved FREDDIE RIVERA
PLUMBING-Rough 2/13/2026 Approved FREDDIE RIVERA
HVAC-Rough 2/19/2026 Partial Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 2/19/2026 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 2/23/2026 Approved FREDDIE RIVERA
Green Building Rough 2/23/2026 Approved FREDDIE RIVERA
HVAC-Rough 2/23/2026 Partial Approval FREDDIE RIVERA
MERV13>=Rough 2/23/2026 Approved FREDDIE RIVERA
Special/Order Compliance 2/23/2026 Partial Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 2/23/2026 Approved FREDDIE RIVERA
Wood Frame 2/23/2026 Not Ready for Inspection FREDDIE RIVERA
Insulation 3/2/2026 Approved FREDDIE RIVERA
Drywall Nailing 3/11/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/11/2026 Partial Approval FREDDIE RIVERA
Shower Pan 4/14/2026 Partial Approval GEM DE OCAMPO