142 S MARTEL AVE 90036
Certificate Information: 142 S MARTEL AVE 90036
- Application / Permit
- 25010-30000-00406
- Plan Check / Job No.
- B25WL00611
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | RICHARD GARCIA |
| Corrections Issued | 2/1/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 2/6/2025 | APPLICANT |
| Applicant returned to address corrections | 3/27/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 4/29/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 5/8/2025 | AMY GUEVARRA |
| Issued | 5/12/2025 | APPLICANT |
| CofO in Progress | 11/19/2025 | JOSH MEISTER |
| No Progress | 11/22/2025 | RAUL BARAJAS |
| CofO in Progress | 11/22/2025 | RAUL BARAJAS |
| Permit Finaled | 11/25/2025 | DEROLD HAUFF |
| CofO Issued | 11/25/2025 | DEROLD HAUFF |
| Permit Finaled | 11/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | WALLIE JONG |
| Sewer availability | Cleared | 4/2/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/4/2025 | DAVID VO |
| HPOZ | Cleared | 4/14/2025 | JORGE RUIZ |
| CPC | Cleared | 5/1/2025 | JASON CHAN |
| HPOZ | Cleared | 5/1/2025 | JASON CHAN |
| ZA Case | Cleared | 5/1/2025 | JASON CHAN |
| ZA Case | Cleared | 5/1/2025 | JASON CHAN |
| CPC | Cleared | 5/6/2025 | JORGE RUIZ |
| Miscellaneous | Cleared | 5/6/2025 | JORGE RUIZ |
Contact Information
| Contractor | Rahban Development; Lic. No.: 1089793-B | 812 N ALPINE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/2/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 6/2/2025 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 6/5/2025 | Approved | JOSE MACIAS |
| Deputy Methane Barrier | 6/9/2025 | Conditional Approval | JOSE MACIAS |
| Deputy Methane Barrier | 6/10/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Deputy Methane Barrier | 6/11/2025 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 6/11/2025 | Approved | JOSE MACIAS |
| METHANE-Barrier | 6/11/2025 | Approved | JOSE MACIAS |
| Deputy Reinf. Concrete | 6/12/2025 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 7/1/2025 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 7/1/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Rough | 7/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 7/1/2025 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 7/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 7/18/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 7/18/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 7/18/2025 | Partial Approval | WAYNE REGESTER |
| METHANE-Rough | 7/18/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 7/23/2025 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 7/23/2025 | Approved | JOSE MACIAS |
| Insulation | 8/6/2025 | Approved | JOSE MACIAS |
| Shower Pan | 8/11/2025 | Corrections Issued | JOSH MEISTER |
| Drywall Nailing | 8/13/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/18/2025 | Approved | JOSH MEISTER |
| Shower Pan | 8/18/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 8/21/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 11/13/2025 | Approved | JOSH MEISTER |
| Gas Test | 11/13/2025 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Final | 11/13/2025 | Corrections Issued | JOSH MEISTER |
| PLUMBING-Final | 11/13/2025 | Corrections Issued | JOSH MEISTER |
| Final | 11/18/2025 | OK to Issue CofO | JOSH MEISTER |
| Gas Test | 11/18/2025 | Approved | JOSH MEISTER |
| Green Building Final | 11/18/2025 | Approved | JOSH MEISTER |
| HVAC-Final | 11/18/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 11/18/2025 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | JOSH MEISTER |
| Service/Power Release | 11/18/2025 | Approved | JOSH MEISTER |
| Smoke Detectors | 11/18/2025 | Approved | JOSH MEISTER |