5450 N BOTHWELL ROAD 91356
Certificate Information: 5450 N BOTHWELL ROAD 91356
- Application / Permit
- 25010-20001-05868
- Plan Check / Job No.
- B26LA13239
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN SUPPLEMENTAL TO PERMIT #25010-10000-05868 TO CHANGE USE FROM REC ROOM TO DETACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS 66323(a)(2).
- Permit Issued
- Issued on 6/2/2026
- Issuing Office
- Current Status
- Issued on 6/2/2026
Permit Application Status History
| Submitted | 4/7/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2026 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 4/16/2026 | SAAD LADHANI |
| Corrections Issued | 4/21/2026 | MICHAEL LOPEZ |
| Quality Review Completed | 4/23/2026 | ARMEN JIVALAGIAN |
| Plan Check Approved | 6/2/2026 | MICHAEL LOPEZ |
| Issued | 6/2/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2026 | MICHAEL BROWN |
| BHO/Hillside ordinance | Cleared | 4/24/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 4/24/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/27/2026 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 5/1/2026 | JOHN CONNEALLY |
| Zoning Plan Check | Cleared | 5/26/2026 | SAAD LADHANI |
| GPI Written Notices | Cleared | 6/2/2026 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 6/2/2026 | MANUEL TEJADA |
Contact Information
| Contractor | Ibuild Developers Inc; Lic. No.: 1047195-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Pre-Inspection | 7/22/2026 Time Frame: 2-4 |
| Shower Pan | 7/23/2026 |
| Insulation | 7/23/2026 |
| Drywall Nailing | 7/23/2026 |
Inspection Request History
| Underground Mechanical | 6/8/2026 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/12/2026 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 7/10/2026 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2026 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 7/10/2026 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/10/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/21/2026 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/21/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/21/2026 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 7/21/2026 | Not Ready for Inspection | JOHN KIDWELL |