738 N VENDOME ST 1-2 90026
Certificate Information: 738 N VENDOME ST 1-2 90026
- Application / Permit
- 25010-20001-00720
- Plan Check / Job No.
- B25VN14144
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPLEMENTAL PERMIT TO 25010-20000-00720 TO COLLECT MEP FEES
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Issued | 5/20/2025 | APPLICANT |
| Permit Finaled | 1/26/2026 | FREDDIE RIVERA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
| Engineer | Yu,, Irene; Lic. No.: C68382 | 3411 CAROLINE AVE CULVER CITY, CA 90232 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2025 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 6/4/2025 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 6/10/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Grounding or Bonding | 6/11/2025 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 6/11/2025 | Partial Approval | FREDDIE RIVERA |
| Sewer | 7/2/2025 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 8/15/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/19/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/19/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/22/2025 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/22/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 9/22/2025 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/30/2025 | Approved | FREDDIE RIVERA |
| Insulation | 9/30/2025 | Approved | FREDDIE RIVERA |
| Shower Pan | 9/30/2025 | Approved | FREDDIE RIVERA |
| Wood Frame | 9/30/2025 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 10/14/2025 | Approved | DEVON JACKSON |
| ELECTRICAL-Final | 12/3/2025 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 12/3/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/22/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 12/22/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 1/13/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 1/21/2026 | Approved | FREDDIE RIVERA |
| Final | 1/23/2026 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 1/23/2026 | Approved | FREDDIE RIVERA |