5122 N CALENDA DR 91367
Certificate Information: 5122 N CALENDA DR 91367
- Application / Permit
- 25010-20000-06602
- Plan Check / Job No.
- B25VN37799
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTAHCED COVERED PATIO. **NFPA 13D FIRE SPRINKLERS REQUIRED**
- Permit Issued
- Issued on 3/2/2026
- Issuing Office
- Current Status
- Issued on 3/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2026 | JEROME MAGAT PALMA |
| Corrections Issued | 1/8/2026 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/9/2026 | APPLICANT |
| Plan Check Approved | 3/2/2026 | NAREG ATARIAN |
| Issued | 3/2/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2026 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 1/9/2026 | ROSE STEIN-WENDT |
| Grading Pre-Inspection | Cleared | 1/12/2026 | ALEXANDER HELFER |
| Watercourse | Cleared | 1/27/2026 | JESUS LUNA |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2026 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 2/27/2026 | KURT CORRAL |
| Sewer availability | Cleared | 2/27/2026 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 3/2/2026 | MANUEL TEJADA |
Contact Information
| Contractor | Top Team Builders & Design Inc; Lic. No.: 1069401-B | 13336 VENTURA BLVD SHERMAN OAKS, CA 91423 |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 7/24/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 5/8/2026 | Conditional Approval | TROY SANDERS |
| Deputy Reinf. Concrete | 5/8/2026 | Conditional Approval | TROY SANDERS |
| PLUMBING-Rough | 5/18/2026 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 5/21/2026 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 6/10/2026 | Not Ready for Inspection | TROY SANDERS |
| Deputy Wood Construction | 6/12/2026 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 7/2/2026 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 7/13/2026 | Approved | TROY SANDERS |
| Green Building Rough | 7/13/2026 | Approved | TROY SANDERS |
| Insulation | 7/13/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 7/13/2026 | Partial Approval | TROY SANDERS |
| MERV13>=Rough | 7/13/2026 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 7/13/2026 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 7/13/2026 | Approved | TROY SANDERS |