14023 W KITTRIDGE ST 91405
Certificate Information: 14023 W KITTRIDGE ST 91405
- Application / Permit
- 25010-20000-06535
- Plan Check / Job No.
- B25VN37625
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND MAJOR REMODEL TO KEEP SMALL PORTION OF EXISTING FOOTING OF EXISTING DETACHED GARAGE AND CONVERT GARAGE INTO NEW DETACHED TWO STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(4) *NFPA-13D FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 4/28/2026
- Issuing Office
- Valley
- Current Status
- Issued on 4/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/26/2025 | APPLICANT |
| Assigned to Zoning Architect | 1/15/2026 | KAREN MEZA-MORALES |
| Assigned to Plan Check Engineer | 1/22/2026 | DANIEL ABRAMYAN |
| Corrections Issued | 1/26/2026 | DANIEL ABRAMYAN |
| Quality Review Completed | 1/30/2026 | OMID HEDAYAT |
| Building Plans Picked Up | 2/4/2026 | APPLICANT |
| Plan Check Approved | 4/24/2026 | DANIEL ABRAMYAN |
| Issued | 4/28/2026 | APPLICANT |
Permit Application Clearance Information
| Public Works-Highway Ded. | Cleared | 2/6/2026 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 2/10/2026 | ERNEST TSE |
| Construction near power lines | Cleared | 2/23/2026 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2026 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/28/2026 | LEE GUILBEAUX |
| Address approval | Cleared | 3/26/2026 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/26/2026 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 4/8/2026 | KAREN MEZA-MORALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 7/23/2026 |
| ELECTRICAL-Rough | 7/23/2026 |
| Interior/Exterior Lathing | 7/23/2026 |
| PLUMBING-Rough | 7/23/2026 |
| HVAC-Rough | 7/23/2026 |
Inspection Request History
| PLUMBING-Rough | 5/14/2026 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/19/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2026 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 7/8/2026 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2026 | Approved | VINCENT HANLEY |