14021 W KITTRIDGE ST 91405

Certificate Information: 14021 W KITTRIDGE ST 91405

Application / Permit
25010-20000-06534
Plan Check / Job No.
B25VN37625
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(4) *NFPA-13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 4/28/2026
Issuing Office
Valley
Current Status
Issued on 4/28/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/26/2025 APPLICANT
Assigned to Zoning Architect 1/15/2026 KAREN MEZA-MORALES
Assigned to Plan Check Engineer 1/22/2026 DANIEL ABRAMYAN
Corrections Issued 1/26/2026 DANIEL ABRAMYAN
Quality Review Completed 1/30/2026 OMID HEDAYAT
Building Plans Picked Up 2/4/2026 APPLICANT
Plan Check Approved 4/24/2026 DANIEL ABRAMYAN
Issued 4/28/2026 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 2/10/2026 ERNEST TSE
Construction near power lines Cleared 2/23/2026 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 2/28/2026 LEE GUILBEAUX
Sewer availability Cleared 2/28/2026 LEE GUILBEAUX
Address approval Cleared 3/26/2026 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/26/2026 LEE GUILBEAUX
Zoning Plan Check Cleared 4/8/2026 KAREN MEZA-MORALES

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 7/23/2026    Time Frame: 10-12
ELECTRICAL-Rough 7/23/2026    Time Frame: 10-12
Interior/Exterior Lathing 7/23/2026    Time Frame: 10-12
PLUMBING-Rough 7/23/2026    Time Frame: 10-12
HVAC-Rough 7/23/2026    Time Frame: 10-12

Inspection Request History

PLUMBING-Rough 5/14/2026 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 5/19/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/3/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/25/2026 Partial Approval VINCENT HANLEY
Deputy Wood Construction 7/8/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/9/2026 Approved VINCENT HANLEY