7721 N MINSTREL AVE 91304
Certificate Information: 7721 N MINSTREL AVE 91304
- Application / Permit
- 25010-20000-06531
- Plan Check / Job No.
- B25VN37619
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per GC 66323(a)(2)
- Permit Issued
- Issued on 2/7/2026
- Issuing Office
- Current Status
- Issued on 2/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2026 | SHANGQIN XIE |
| Corrections Issued | 1/5/2026 | SHANGQIN XIE |
| Plan Check Approved | 2/5/2026 | SHANGQIN XIE |
| Issued | 2/7/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2026 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2026 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/12/2026 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/13/2026 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 2/3/2026 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Armendillo Design-Build; Lic. No.: 959696-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/9/2026 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 4/1/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/1/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/1/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/20/2026 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/20/2026 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/20/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/20/2026 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/20/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/24/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/24/2026 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/24/2026 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 4/24/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 4/30/2026 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 4/30/2026 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/1/2026 | Approved | CHRIS CHRISTENSEN |
| Sewer | 5/1/2026 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 5/1/2026 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/1/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/5/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/5/2026 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/5/2026 | Partial Approval | CHRIS CHRISTENSEN |