7721 N MINSTREL AVE 91304

Certificate Information: 7721 N MINSTREL AVE 91304

Application / Permit
25010-20000-06531
Plan Check / Job No.
B25VN37619
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per GC 66323(a)(2)
Permit Issued
Issued on 2/7/2026
Issuing Office
Current Status
Issued on 2/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2025 APPLICANT
Assigned to Plan Check Engineer 1/2/2026 SHANGQIN XIE
Corrections Issued 1/5/2026 SHANGQIN XIE
Plan Check Approved 2/5/2026 SHANGQIN XIE
Issued 2/7/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/12/2026 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/12/2026 BIAINA HARITUNIAN
Sewer availability Cleared 1/12/2026 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/13/2026 BIAINA HARITUNIAN
Construction near power lines Cleared 2/3/2026 GEVORK KARAPETYAN

Contact Information

Contractor Armendillo Design-Build; Lic. No.: 959696-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2026 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/9/2026 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/1/2026 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/1/2026 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 4/1/2026 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/20/2026 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/20/2026 Approved CHRIS CHRISTENSEN
Green Building Rough 4/20/2026 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 4/20/2026 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 4/20/2026 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/24/2026 Approved CHRIS CHRISTENSEN
Green Building Rough 4/24/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/24/2026 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/24/2026 Approved CHRIS CHRISTENSEN
Underground Mechanical 4/24/2026 Partial Approval CHRIS CHRISTENSEN
Insulation 4/30/2026 Approved CHRIS CHRISTENSEN
Shower Pan 4/30/2026 Approved CHRIS CHRISTENSEN
Insulation 5/1/2026 Approved CHRIS CHRISTENSEN
Sewer 5/1/2026 Approved CHRIS CHRISTENSEN
Shower Pan 5/1/2026 Approved CHRIS CHRISTENSEN
Underground Mechanical 5/1/2026 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 5/5/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/5/2026 Approved CHRIS CHRISTENSEN
Underground Mechanical 5/5/2026 Partial Approval CHRIS CHRISTENSEN