733 N SWARTHMORE AVE 90272

Certificate Information: 733 N SWARTHMORE AVE 90272

Application / Permit
25010-20000-06427
Plan Check / Job No.
B25VN37384
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
****2025 WILDFIRE REBUILD EO 1 ELIGIBLE PROJECT****NEW 26'-4 1/2" X 62'-1 1/2" 2-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/5/2026
Issuing Office
Current Status
Issued on 5/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2025 APPLICANT
Assigned to Plan Check Engineer 12/23/2025 RAPHAEL ROSAS
Corrections Issued 12/30/2025 RAPHAEL ROSAS
Quality Review Completed 12/30/2025 STEVEN KIM
Building Plans Picked Up 1/2/2026 APPLICANT
Applicant returned to address corrections 1/29/2026 RAPHAEL ROSAS
Plan Check Approved 4/13/2026 RAPHAEL ROSAS
Issued 5/5/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/6/2026 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/6/2026 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/6/2026 DAVID LOPEZ
Sewer availability Cleared 1/6/2026 DAVID LOPEZ
Low Impact Development (LID) Cleared 1/30/2026 MARTIN FRAGOSO
Hydrant and Access approval Cleared 2/2/2026 RUEL COLE
SB8 RUD Cleared 3/18/2026 OLIVIA JIN

Contact Information

Contractor Jensen Const Inc; Lic. No.: 787346-B 2222 FOOTHILL BLVD V E-548      LA CANADA, CA 91011
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2026 Partial Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 5/27/2026 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 5/27/2026 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 6/2/2026 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 6/8/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/22/2026 Approved RYAN SALAZAR
Deputy Reinf. Concrete 6/24/2026 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/8/2026 Corrections Issued STEPHANIE SWANSON