821-823 S MALCOLM AVE 90024

Certificate Information: 821-823 S MALCOLM AVE 90024

Application / Permit
25010-20000-06269
Plan Check / Job No.
B25VN36705
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY SFD WITH ATTACHED TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AS PER GC 66323(a)(1) , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/26/2026
Issuing Office
Current Status
Issued on 3/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2025 APPLICANT
Assigned to Zoning Architect 12/19/2025 KATAYOUN JANGI NEJAD
Assigned to Plan Check Engineer 12/24/2025 RARES BODEA
Corrections Issued 12/30/2025 RARES BODEA
Quality Review Completed 12/30/2025 STEVEN KIM
Building Plans Picked Up 1/7/2026 APPLICANT
Plan Check Approved 3/26/2026 RARES BODEA
Issued 3/26/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/26/2026 JESUS CISNEROS
Low Impact Development (LID) Cleared 1/29/2026 SARAH YOUSSEF
Hydrant and Access approval Cleared 2/3/2026 LAVEON RIDER
Eng Process Fee Ord 176,300 Cleared 2/6/2026 JESUS CISNEROS
Sewer availability Cleared 2/6/2026 JESUS CISNEROS
Historic monument Cleared 3/10/2026 LAMBERT GIESSINGER
Permit Cleared 3/13/2026 JEFF LOREDO
Roof/Waste drainage to street Cleared 3/13/2026 JEFF LOREDO
Trees in Parkway Cleared 3/13/2026 RICHARD SANCHEZ
Specific Plan Cleared 3/16/2026 RICHARD WOO
Zoning Plan Check Cleared 3/25/2026 KATAYOUN JANGI NEJAD
GPI Written Notices Cleared 3/26/2026 RARES BODEA
Grading Pre-Inspection Cleared 3/26/2026 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2026 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 5/4/2026 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/20/2026 Approved DAVID SCANTLIN
HVAC-Rough 6/5/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 6/5/2026 Approved DAVID SCANTLIN