10535 W CHANDLER BLVD 91601

Certificate Information: 10535 W CHANDLER BLVD 91601

Application / Permit
25010-20000-05993
Plan Check / Job No.
B25VN36219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
27'-0" X 31'-9" ACCESSORY DWELLING UNIT ADDITION TO (E) SFD PER GCS 66323(a)(1). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 12/31/2025
Issuing Office
Valley
Current Status
Issued on 12/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2025 APPLICANT
Assigned to Plan Check Engineer 12/15/2025 ARTIN ZARUKIAN
Corrections Issued 12/15/2025 ARTIN ZARUKIAN
Building Plans Picked Up 12/17/2025 APPLICANT
Plan Check Approved 12/31/2025 NAREG ATARIAN
Issued 12/31/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/19/2025 STEVE MELGAR
Roof/Waste drainage to street Cleared 12/19/2025 STEVE MELGAR
Metro Rail approval Cleared 12/29/2025 ARTIN ZARUKIAN
Eng Process Fee Ord 176,300 Cleared 12/30/2025 STEVE MELGAR
Sewer availability Cleared 12/30/2025 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/6/2026 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 2/19/2026 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/25/2026 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 3/18/2026 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/14/2026 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/14/2026 Conditional Approval GAREN HAYRAPETYAN
Green Building Rough 4/14/2026 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 4/14/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 4/14/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 4/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/24/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 4/24/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/13/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 5/13/2026 Approved GAREN HAYRAPETYAN
Insulation 5/13/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/13/2026 Approved GAREN HAYRAPETYAN
Drywall Nailing 5/21/2026 Approved GAREN HAYRAPETYAN