719 N ALMA REAL DR 90272
Certificate Information: 719 N ALMA REAL DR 90272
- Application / Permit
- 25010-20000-05987
- Plan Check / Job No.
- B25VN36190
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ****2025 WILDFIRE INELIGIBLE REBUILD**** REBUILD 2 STORY SFD WITH HABITABLE BASEMENT AND ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/10/2026
- Issuing Office
- Current Status
- Issued on 3/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2025 | RARES BODEA |
| Corrections Issued | 12/16/2025 | RARES BODEA |
| Quality Review Completed | 12/16/2025 | STEVEN KIM |
| Building Plans Picked Up | 12/17/2025 | APPLICANT |
| Applicant returned to address corrections | 1/22/2026 | RARES BODEA |
| Plan Check Approved | 2/17/2026 | RARES BODEA |
| Issued | 3/10/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2025 | CINDY QI |
| Permit | Cleared | 12/15/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/15/2025 | CINDY QI |
| Sewer availability | Cleared | 12/15/2025 | CINDY QI |
| Low Impact Development (LID) | Cleared | 12/18/2025 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 12/24/2025 | KURT CORRAL |
| Trees in Parkway | Cleared | 1/12/2026 | MIGUEL ORNELAS |
| Excavation more than 5-ft deep | Cleared | 1/28/2026 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/17/2026 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 2/17/2026 | RARES BODEA |
Contact Information
| Contractor | Arbib & Sons Construction Inc; Lic. No.: 1095253-B | 5001 TEXHOMA AVENUE ENCINO, CA 91316 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 7/23/2026 Time Frame: 11-1 |
Inspection Request History
| Pre-Inspection | 3/16/2026 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/21/2026 | Partial Approval | STEPHANIE SWANSON |
| Underground Mechanical | 4/21/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 4/22/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/12/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/22/2026 | Partial Approval | STEPHANIE SWANSON |
| Underground Mechanical | 6/4/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2026 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 7/14/2026 | Approved | JESUS PINEDA |