17121 W VALERIO ST 91406
Certificate Information: 17121 W VALERIO ST 91406
- Application / Permit
- 25010-20000-05742
- Plan Check / Job No.
- B25VN34949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New 1 story detached ADU per GC 66323(a)(2)
- Permit Issued
- Issued on 2/4/2026
- Issuing Office
- Current Status
- Issued on 2/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2025 | ADAM HEGAZI |
| Corrections Issued | 12/9/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 1/30/2026 | ADAM HEGAZI |
| Plan Check Approved | 2/3/2026 | SUNMIN LEE |
| Issued | 2/4/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/15/2025 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/31/2026 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 2/2/2026 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Sewer | 6/8/2026 Time Frame: 12-2 |
| Underground Mechanical | 6/8/2026 Time Frame: 12-2 |
Inspection Request History
| PLUMBING-Rough | 3/25/2026 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/31/2026 | Approved | KIRK SANDERS |
| Special/Order Compliance | 3/31/2026 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/27/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/27/2026 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 4/27/2026 | Approved | KIRK SANDERS |
| Special/Order Compliance | 4/27/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/1/2026 | Partial Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/8/2026 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 5/12/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 5/18/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 5/18/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/27/2026 | Approved | RAUL OLAGI |
| Shower Pan | 5/27/2026 | Approved | RAUL OLAGI |